Publisher’s version / Version de l'éditeur:
Technical Note (National Research Council of Canada. Division of Building Research), 1962-01-01
READ THESE TERMS AND CONDITIONS CAREFULLY BEFORE USING THIS WEBSITE. https://nrc-publications.canada.ca/eng/copyright
Vous avez des questions? Nous pouvons vous aider. Pour communiquer directement avec un auteur, consultez la
première page de la revue dans laquelle son article a été publié afin de trouver ses coordonnées. Si vous n’arrivez pas à les repérer, communiquez avec nous à [email protected].
Questions? Contact the NRC Publications Archive team at
[email protected]. If you wish to email the authors directly, please see the first page of the publication for their contact information.
NRC Publications Archive
Archives des publications du CNRC
For the publisher’s version, please access the DOI link below./ Pour consulter la version de l’éditeur, utilisez le lien DOI ci-dessous.
https://doi.org/10.4224/20338463
Access and use of this website and the material on it are subject to the Terms and Conditions set forth at Modifications to Inuvik, N.W.T. Airstrip Ground Temperature Installations
Johnston, G. H.
https://publications-cnrc.canada.ca/fra/droits
L’accès à ce site Web et l’utilisation de son contenu sont assujettis aux conditions présentées dans le site LISEZ CES CONDITIONS ATTENTIVEMENT AVANT D’UTILISER CE SITE WEB.
NRC Publications Record / Notice d'Archives des publications de CNRC:
https://nrc-publications.canada.ca/eng/view/object/?id=bd2ea711-be35-4b9b-b252-28a350c5efa2 https://publications-cnrc.canada.ca/fra/voir/objet/?id=bd2ea711-be35-4b9b-b252-28a350c5efa2
DIVISION OF BUILDING RESEARCH
TECHN][CAlL
NOT FOR PUBLICATION
360
FOR INTERNAL USE
PREPARED BY G. H. Johnston CHECKED BY CBC APPROVED BY NBH
PREPARED FOR
Record Purposes
January 1962
SUBJECT
MODIFICATIONS TO INUVIK, N.W.T. AIRSTRIP
GROUND TEMPERATURE INSTALLATIONS
In March QYUWセヲッオイ thermocouple cables were installed at the Inuvik, N.W.T. airstrip to measure ground temperatures. Two cables were placed under the centre line of the runway, one at the centre of the parking apron and a fourth in an undisturbed area adjacent to the airport (Fig. 1). These installations were made to determine the effect of the crushed rock fill (of which the airstrip is constructed) on permafrost conditions in the underlying foundation material and the rate of seasonal thaw and freeze of the fill.
The work was undertaken as a co-operative venture of the Department of Transport and the Division of BUilding
Research of the National Research Council. The Division supplied all the equipment and supervised the installation of the
instruments. In turn the Department of Transport undertook to make the observations of ground temperatures that have
been taken on a weekly basis since June 1957. Full information on these installations, including details of the ゥョセエイオュ・ョエウ
and soil and permafrost conditions at the site, have already been given to the Department of Transport. Further details
of the completed installations are given on Drawing No. AKLAVIK 26, Department of Transport, Air Services Branch, Construction Division, Edmonton District dated May 1958.
The purpose of this note is to describe certain modifications which were made to the three thermocouple installations located on the airstrip, in September 1961 by members of the Division of Building Research. These changes
2
-were essentially made to simplify the taking of readings and to provide a more convenient installation.
Description of Original Installations
The airstrip thermocouple cables were installed in test pits dug to a depth of 15 ft below the original ground'
surface prior to the construction of the airstrip. The top
portion of each of the cables, which contained the sensing points for measuring temperatures in the fill, was positioned as the crushed rock was placed during the construction period. Each cable terminated in a special, weatherproof switch box enclosed by a heavy steel box, about 2 ft square, to protect
it from damage. When the airs·trip was completed, the boxes
were located just under (from 6 - 18 in.) the surface of the fill and directly above the thermocouple cable in the ground. The cable located in the undisturbed area terminated in a similar switch box placed on the ground surface.
Each time readings were taken it was necessary to remove the crushed rock covering the switch box and'when the
readings were completed, to 「。」ォセヲゥャャ and compact the disturbed
fill. During the Winter, when the snow cover on the airstrip
was rolled and compacted,
6 - 9
in. of very dense snow or icehad to be removed as well as the frozen backfill covering the
switch box. Not only was this a tedious and time consuming
chore, but the removal and subsequent replacement of this material each week left a soft spot on the runway and apron at each location, that could prove hazardous to aircraft using the airport.
Ground エ・ュー・イセエオイ・ measurements were obtained
initially with a portable potentiometer. The sensitivity
of this instrument is adversely affected when used with installations of long lead length and consequently of large
resistance. The airstrip installation leads were near the
maximum permissible length so that the switch boxes had to be placed in the fill and could not be moved to a more
con-venient position. To counteract this, the Division modified
a laboratory-type electronic temperature indicator for field
use. The sensitivity of this instrument is not affected by
the lead lengths normally used for ground. temperature
installations. Powered by a gas engine driven generator, it
has been used to measure all ground temperatures at the airstrip since the fall of 1960.
With this instrument now in use, the decision to move the switch boxes to a more convenient location could be
made. In September 1961, they were moved from under the
surface of the fill, at the centre of the runway and the parking apron, to the sides'of the airstrip where they were
placed above the ground surface. The old location of the switch boxes, under the centre of the fill, would prove troublesome if the decision to pave the airstrip were to be made in the future.
Modifications to the Ground Temperature Installations
The modifications made to the three airstrip
instal-lations included: the removal of the rotary selector switches
from the old switch boxes, the splicing of one セョ、 of lengths
of special thermocouple lead wire to the ground temperature measuring thermocouple wires in the old switch' box (which was left in place in the fill), and the connection of the other end of the special lead cables to another type of rotary
ウ・ャ・」エセイ switch housed in specially made weatherproof switch
boxes at the edge of the fill. The special lead cables were
placed inside black polyethylene pipe and buried in a trench
about 12 in. deep under the surface of the fill. The cable
was placed at the same depth as the runway lighting cables but could not be buried any deeper because of large-size rock
encountered at that depth. The trench was excavated from the
location of tne original switch box at the centre of the
airstrip to the new location of the switch box at the edge of the fill, backfilled and compacted by a grader •.
At the three airstrip locations, ground temperatures were measured by three thermocouple points placed at each of the follOWing depths - 2.5, 5, 10 and 15 ft below the original ground sUrface, at the ground surface and also at ゥセエ・イカ。ャウ
of 2, 4, 6 and 8 ft above the ground surface in the rock fill. In addition, one thermocouple point measured the air
tempera-ture in the switch box. A total of 28 thermocouple measuring
points were therefore connected to a 28-point LEWIS switch. Two 12-point LEEDS and NORTHRUP rotary selector switches were used in the new switch boxes for each installation
modified. Thus, four measuring points, the switch box 。ゥイセ
temperature thermocouple and the three measuring points placed in the fill 8 ft above the original ground surface, have been eliminated at each of the newly modified airstrip installations.
Lengths of "THERlVIO-CABLE" type PPeK-12-20-DD,
containing 12 copper-constantan wire pairs were used as lead cables from the thermocouple installations to the new switch
boxes. The individual conductors in this cable, are covered
with polyvinyl chloride and the 9undle of conductors is
wrapped with aluminum-backed Mylar tape. The cable is
finished with an over-all jacket of polyethylene. The wires
are of premium grade copper and constantan. Two lengths of
"Thermo-Cablen were used at each installation and were placed
4
-pipe (C.G.S.B. spec. 41-GP-5A) for protection and buried side by sid'e in the trenoh. A total length of 1000 ft of "Thermo-Cable" was used for the three installations.
At each installation the lead cables entered the old switch box (where the splice was made) thrOUgh a hole cut in the side of the protective steel box. The splice was made by tWisting the matching copper and constantan wires together and wrapping each splice individually with electrician's tape. The first 12 pairs of wires were spliced to "Thermo-Cable" lead cable No. 1 in order from the lowest thermocouple point in the ground. The second group of 12 pairs was then spliced to cable No.2. When all splices were made, a 9-in. length of I-in. dia. polyethylene pipe, that had been slipped over one end of the 3/4-in. protective plastic pipe before the connections were made, was then pulled over the junction and filled With sealing compound. The switch box lid was then· tightly clamped in place and the heavy steel cover replaced on the protective box. Fine crushed rock backfill was then carefully placed and tamped around and over the installations and brought to grade.
The two lead cables enter the new switch boxes, which consist of a 9-in. length of 6-in. dia. ウセ・・ャ pipe supported on three legs, through special connectors on the bottom plate which is welded to the main body of the box. The copper wires from each cable are soldered to the appro-priate lugs on the two switches in the box. All constantan wires from both oables are connected to a common oonstantan wire by a Marr conneotor. The common copper leads from the
switohes and the common constantan lead terminate at a
special oonnector in the box to whioh the lead wire from the reading instrument is attaohed when readings are taken. When the lid is placed on the switch box and tightened in place by the thumb screws provided, the switches and connections are enolosed in a weatherproof box.
The only modification made to the ground tempera-ture installation in the undisturbed area near the airport was the placing (in the old type switch box which was not removed) of a new type of connector to which the lead cable from the measuring instrument is connected to take readings. The 28-point LEWIS type switch is still used, and 28 tempera-ture measurements are obtained at this installation. All soldered constantan connections at each of the four installa-tions have been eliminated by the use of Marr connectors.
Details of the location of the ground temperature installations, the lead cables and the new switch boxes are given in Fig. 1. The form (Northern N-l) used to record the ground temperature observations has been revised as a result of the modifications made; a copy of this is attached to this
5
-note. It will be noted that thermocouple point four at
installation No.3, indicates the temperature in the junction box (old switch box) under the airstrip. This ground tempera-ture point in the ground was found to be dead; the copper-constantan pair in the "Thermo-Cable" lead cable, at the
junction box, splice, was then made into a temperature measuring point.
Aclmowledgment
The co-operation and assistance provided by the Department of Transport Inuvik airport maintenance staff
(Mr. R. J. Aubrey, Airport Manager) during the course of this work is gratefully aclmowledged.
,
• -INUVIK N.W. T. AIRSTRIP GROUND TEMPERATURE OBSERVER _ DATE _NORTHERN RESEARCH GROUP DIVISION OF BUILDING RESEARCH NATIONAL RESEARCH COUNCIL
FORM N-I (REVISED OCT. 1961)
#1
#2
#3
#4
0 UNDISTURBED 0 WEST END EAST END
SWITCH DEPTH AREA DEPTH PARKING APRON AIRSTRIP AIRSTRIP POINT (FT) TEMP (OF) (FT) TEMP (OF) TEMP (OF) TEMP (OF)
I 15 15 2 15 15 3 15 15 4 10 10 0 5 10 10 6 10 10 7 5 5 8 5 5 9 5 5 10 4 2·5 II 4 2·5 12 4 2·5 13 3 0 14 3 0 15 3 0 16 2 -2 17 2 -2 18 2 -2 19 I -4 20 I -4 21 I -4 22 0·5 -6 23 0·5 -6 24 0·5 -6 .. 25 0 REMARKS 2& (j 27 0 28 AIR SNOW
I
DEPTHo DEPTH BELOW ORIGINAL GROUND SURFACE
NEGATlVE SIGN INDICATES AEIOVE ORIGINAL GROUND SURFACE (ie. IN ROCK FILL) • TEMPERATURE IN JUNCT I-ON BOX - ONE FOOT BELOW
ROA.O TO TOW/lJSITE. L1Gl-l1 . ,
e
CABL£,. "1 LlG\.IT "'7PLAN OF AIRSTRIP
INUVI K N.W.T.
o soc 1000FT. • • • • • I • . . • I sセo|jloeNrN Ol= RUt-.JWA,VR.U t-JWA,'l L.IGI-\-T':o
51 @ 2,0::>' ,.,... \J,I