Invited Professional Development Seminar - BIM - a Tool to Optimize Building Construction

N/A
N/A
Protected

Academic year: 2021

Partager "Invited Professional Development Seminar - BIM - a Tool to Optimize Building Construction"

Copied!
20
0
0

Texte intégral

(1)

Publisher’s version / Version de l'éditeur:

Vous avez des questions? Nous pouvons vous aider. Pour communiquer directement avec un auteur, consultez la Questions? Contact the NRC Publications Archive team at

PublicationsArchive-ArchivesPublications@nrc-cnrc.gc.ca. If you wish to email the authors directly, please see the first page of the publication for their contact information.

https://publications-cnrc.canada.ca/fra/droits

L’accès à ce site Web et l’utilisation de son contenu sont assujettis aux conditions présentées dans le site LISEZ CES CONDITIONS ATTENTIVEMENT AVANT D’UTILISER CE SITE WEB.

Invited Seminar at FP Innovations, Quebec City: 15 March 2011, Quebec City, Quebec [Proceedings], 2011-03-15

READ THESE TERMS AND CONDITIONS CAREFULLY BEFORE USING THIS WEBSITE.

https://nrc-publications.canada.ca/eng/copyright

NRC Publications Archive Record / Notice des Archives des publications du CNRC :

https://nrc-publications.canada.ca/eng/view/object/?id=016a9cab-977a-426a-9e83-1ee379585173 https://publications-cnrc.canada.ca/fra/voir/objet/?id=016a9cab-977a-426a-9e83-1ee379585173

This publication could be one of several versions: author’s original, accepted manuscript or the publisher’s version. / La version de cette publication peut être l’une des suivantes : la version prépublication de l’auteur, la version acceptée du manuscrit ou la version de l’éditeur.

Access and use of this website and the material on it are subject to the Terms and Conditions set forth at

Invited Professional Development Seminar - BIM - a Tool to Optimize Building Construction

(2)

1

Institute for Research in Construction

BIM

– A Tool to Optimize Building

Construction

Centre for Computer-assisted Construction Technology

John Dickinson, Ph.D., P. Eng. John.Dickinson@nrc.gc.ca

15 March 2011

Institute for Research in Construction

National Research Council

• National organization, federal government agency

• Over 4,200 full-time employees; over 1,446 guest workers • Labs and facilities across Canada

• Dissemination of S&T information to industry and scientific community

• Provides essential elements of national S&T infrastructure

(3)

Institute for Research in Construction

The NRC Centre for Computer-assisted Construction Technologies

Part of NRC Institute for Research in Construction

Research and development driven by four issues in construction industry:

• the need to improve productivity

• growing complexity of built environments • sustainable development

• changing workforce demographics

NRC-CCCT

Increasing productivity of the construction

life-cycle through applied technology

• Computational tools to aid design, implementation & management of built resources

• Decision support tools

• Digital knowledge & information management • Tools and practices to improve the efficiency of the

(4)

3

Institute for Research in Construction

Presentation Outline

What is BIM?

 Why care?  Intent or promise  Definition  Game Changer

BIM @ work

 In use  Organisations  Standards

Relevance to Wood

 Products & Systems  BIM Capabilities

 Near-term  Longer-term

Institute for Research in Construction

What is BIM?

Why care?

BIM Intent or Promise

Defining BIM

Game Changer

(5)

Institute for Research in Construction

Why Care?

Lost Money

2004 NIST report

(Cost Analysis of Inadequate Interoperability in the U.S. Capital Facilities Industry)

$15.8B/y lost due to poor interoperability

• 1-2% industry’s revenue

2/3 during operations and maintenance phase

http://www.bfrl.nist.gov/oae/publications/gcrs/04867.pdf

The Promise:

Interoperability

(6)

5

Institute for Research in Construction

BIM in Short

– Interoperability

9 h ttp :// e e td n e w s. lb l.g o v/ n l0 3 /im a g e s/ b liss -sp ira l.p n g Asti.com

Institute for Research in Construction

BIM Standards Organisations

principal product is the National BIM Standard

(7)

Institute for Research in Construction

BIM Lifecycle View

http://www.jotne.com/project-information-owners.442302-79297.html

CAD vs. BIM

• 2D or 3D

• Lines

• Layers if done properly

• Robust exchange

standards

• No standard way of

adding contextual

• 3D or more

• Physical & functional

elements

• Well-defined collection

of facility data

• Machine interpretable

• Traceability, ownership

4D

– Time

5D

– Cost

(8)

7

Institute for Research in Construction

Potential for Game Changer

• Full/Better solutions up-front

- Mutual understanding, consensus multi-disciplinary approaches

• Avoid late changes

- Miss-understandings - Unforeseen consequences - Less errors/clashes

• Correct materials/tools/people at correct time,

• Offsite work, prefab assemblies

http://www.cenews.com/magazine-article-cenews.com-october-2008-what_does_bim_mean_for_civil_engineers_-6098.html

Communication

Collaboration

Coordination

Institute for Research in Construction

BIM @ Work

BIM In Use

Organisations Backing/Using BIM

Standards

(9)

Institute for Research in Construction

Design

Visualisation

• Architects • Industrial Designers • Functional Analysis • Real Estate • Commercial Property Managers • Interior Decorators h ttp :// m y. o p e ra .co m /ki e n tru cv n /a lb u m s/ sh o w p ic .d m l? a lb u m = 7 2 4 0 1 2 & p ict u re = 9 7 7 9 6 6 2 h tt p :/ / d isco u n t. b in a o ff ice fu rn itu re .co m /2 0 1 0 _ 0 7 _ 0 1 _ a rc h iv e .h tm l

Facility Appearance - Visualisation

Geographical Rendering and Neighbourhood Impact

(10)

9

Institute for Research in Construction

Walkthrough Example

Institute for Research in Construction

Engineer

– Architect Collaboration

- Green/LEED/Sustainable

Orientation Optimization

(11)

Institute for Research in Construction

Engineering - Systems & Structure

h ttp :// w w w .b im o u tso u rci n g .co m /h va c-se rvi ce .h tm http://www.pmengineer.com/Art icles/Cover_Story/2009/02/01/T he-Benefits-of-BIM-in-Plumbing-Design h ttp :// w w w .risa te ch e sp a n o l.co m /im a g e s/ p a rtn e rs/ re vi t/r isa R e vi tL in k. jp g

Facility Performance

– Owners/Ops

Consummation Variation on a year

4,000.00 4,500.00 5,000.00 5,500.00 6,000.00 6,500.00 7,000.00 7,500.00 8,000.00 8,500.00 9,000.00 J a n J a n J a n J a n J a n F e b F e b F e b F e b M a r M a r M a r M a r A p r A p r A p r A p r A p r M a y M a y M a y M a y J u n J u n J u n J u n Jul J u l J u l J u l J u l A u g A u g A u g A u g S e p S e p S e p S e p S e p O c t O c t O c t O c t N o v N o v N o v N o v D e c D e c D e c D e c D e c E n e rg y C o n s u m m a ti o n ( k Wh ) Average 2003 Average 2004 Average 2005 Average 2006 Average 2007

Energy analysis, comfort, controls automation

2 3

1

4 N

Daily Direct Radiation Average

100 200 300 400 500 600 700 800 900 1000 D ir e c t R a di a ti on ( k J /m 2 )

(12)

11

Institute for Research in Construction

Analysis Simulations

Institute for Research in Construction

General Contractors

– VDC

• Constructability – clashes before workers onsite

• Scheduling – planning, slippage

• Reduce # and $ of RFIs – models vs. drawings

• Bid – 3D-4D visualization of process

• Lower uncertainty  reduced contingency

• Coordination meetings / Progress tracking

• Materials / Supplies

(13)

Institute for Research in Construction

General Contractor

Workface planning, scheduling, coordination

• General Contractors

h ttp :// w w w .ca d a lyst .co m /a e c/ b im -and -p ro je ct -p la n n in g-1 -2 -3 -re vi t-t u to ria l-3 5 2 0 http://www.youtube.com/watch?v=FE_zYiltsAw

Accurate Cost Estimating

http://www.cadalyst.com/aec/army-corps-drawn-bim-design-3764

(14)

13

Institute for Research in Construction

Bottom Line

– GC

Partial VDC project vs. Benchmark projects

• 50% RFIs

• Per-RFI cost 1/5

th

• Over-runs costs 1/15

th

typical

• Project completed months ahead schedule

- Benchmarks months delayed

http://www.tpm.com/component/content/article/1-latest-news/513-how-bim-is-being-utilized-by-general-contractors-and-its-benefits-a-general-contractor

Institute for Research in Construction

Bottom Line

– Owner

Tendency to:

• Better understand what they are buying

- Improved upfront design

- Less requests for changes

• Get better quality

- built as-planned

- less problems/ad-hoc solutions/products • Future

(15)

Institute for Research in Construction

Early Canadian Industry Adopters

EllisDon HIP Architects RCNA Stantec Halsall Associates PCL Construction PFLA Inc DOWCO Group ... more

Organisations

American Institute of Architects Associated General Contractors General Services Administration The FIATECH Consortium

Construction Specifications Institute Canada/US Green Building Council Canadian Construction Assoc. Canada BIM Council

Steel Construction Institute Institute for BIM in Canada

(16)

15

Institute for Research in Construction

Regional Adoptions

Scandinavia:

Finland, Norway, Denmark

Australia

Singapore

US:

GSA, universities, army, NASA

Canada:

Alberta, BC, Montreal?

Western European Practitioners:

36% (2010)

USA Practitioners:

48% (2010)

http://images.autodesk.com/adsk/files/business_value_of_bim_in_europe_2010_final_new.pdf

Institute for Research in Construction

Interoperability at a glance

– IFC

IFC

: Industry Foundation Classes (.ifc)

• Objects: spaces, basic building elements, ... • Certification program

• Model View Definitions – legal subsets of data

Two common IFC2x3 model views:

• Coordination View – design & construction • Basic FM Hand Over – construction & operator

- COBie: Construction Operations Building information exchange

(17)

Institute for Research in Construction

Interoperability

CIS/2.1 & gbXML

CIS/2.1

: CIMsteel Integration Standards Release 2

• Steel Construction Institute • Structural steelwork industry • Detailing, analysis, fabrication, …

gbXML

: green building XML

• Mostly for energy and comfort modelling packages • Chunks facility into contiguous spaces

• Equipment

BIM Relevance to Wood

Products and Systems

BIM Capabilities

Near-term

Longer-term

(18)

17

Institute for Research in Construction

BIM

Design & Material Specification •Mfg Catalogue •Specifications Assemblies Analysis •Codes / Reg. •Acoustics / Fire •... Green Certification •LEED •BREEAM •... Takeoffs •Material •Labour •Supply chain Operations •Maintenance •Status •Warrantee Demolition •Reclamation •Recycling

BIM for Manufacturers

Institute for Research in Construction

BIM: Value-adding

Early Material Selection in Design Visualisation & Performance Based on Specs Construction & Supply Chain Integration Orders from Manufacturers Manufacturers BIM Product Specifications

(19)

Institute for Research in Construction

BIM Capabilities

– Near-Term

- Design tools –Revit(Framing Tool), - Design and Analysis tools:

- Tekla& Risa

- Parametric librariesof wood & composite products supply chain

- Limited code checking or

requirements assessment

- Link to Fabrication (Cadwork)

- Still manual CAD and not BIM – joins, cuts, machining

BIM Capabilities

– Far-Term

- Link to Analysis

- Improved Structural

- Fire (NIST – FDS) Geometry and common properties - Acoustic (not soon) – digital guides

- Design to Fabrication (need CIS/2 for Wood)

- Automation – First in CAD, later BIM? - Standards for Stakeholders

- Analysis, Process, Materials, Parts, Assembly

(20)

19

Institute for Research in Construction

Key Points

• Exchange and collaborate with partners • Avoid re-entry

• Game changer

BIM Interoperability

• Design • Construction

• Analysis – Code, Lighting, Water, Energy, Basic Structure

Significant Penetration

• Analysis – Structure, Fire, ... • Design to Fabrication

Future for Wood

Institute for Research in Construction

Contact Details

John Dickinson Tel: (519) 430-7123

John.Dickinson@nrc.gc.ca

Centre for Computer-Assisted Construction Technologies National Research Council Canada

800 Collip Circle, London, ON N6G 4X8

Références

Documents relatifs

This paper studies a new spectral analysis strategy for detecting, characterizing and classifying spectral structures of an unknown stationary process.. A sum of an unknown number

Possible and necessary winners correspond to simple existential and universal quan- tification, or, in epistemic logic terms, to possibility and knowledge: x is a necessary winner if

A Survey Simulator takes an intrinsic orbital model (from, for example, the output of a dynamical Kuiper belt emplacement simulation) and applies the survey biases, so that the

Cet article expose les résultats des recherches menées à ce sujet, comparant la résistance au feu des poteaux en béton haute résistance et celle des poteaux à résistance normale,

Although the ECON4SD’s Building Information Model is to be created during or after the design phase, it will be used throughout the various stages of the building Life-cycle. A

Therefore, the estimation of C&D waste, reusable structural components and recycling materials

The use of BIM tool helps construction players to conduct their roles and responsibilities in more efficient and effective by overtake the traditional 2D paper-based

Both respondents believed that BIM is an effective process in managing construction projects by reducing construction problems such as design clashes, design