Publisher’s version / Version de l'éditeur:
Vous avez des questions? Nous pouvons vous aider. Pour communiquer directement avec un auteur, consultez la
première page de la revue dans laquelle son article a été publié afin de trouver ses coordonnées. Si vous n’arrivez pas à les repérer, communiquez avec nous à [email protected].
Questions? Contact the NRC Publications Archive team at
[email protected]. If you wish to email the authors directly, please see the first page of the publication for their contact information.
https://publications-cnrc.canada.ca/fra/droits
L’accès à ce site Web et l’utilisation de son contenu sont assujettis aux conditions présentées dans le site LISEZ CES CONDITIONS ATTENTIVEMENT AVANT D’UTILISER CE SITE WEB.
Student Report; no. SR-2009-12, 2009-01-01
READ THESE TERMS AND CONDITIONS CAREFULLY BEFORE USING THIS WEBSITE.
https://nrc-publications.canada.ca/eng/copyright
NRC Publications Archive Record / Notice des Archives des publications du CNRC : https://nrc-publications.canada.ca/eng/view/object/?id=64664098-1460-4885-82c1-3fd9091ec91e https://publications-cnrc.canada.ca/fra/voir/objet/?id=64664098-1460-4885-82c1-3fd9091ec91e
NRC Publications Archive
Archives des publications du CNRC
For the publisher’s version, please access the DOI link below./ Pour consulter la version de l’éditeur, utilisez le lien DOI ci-dessous.
https://doi.org/10.4224/18238671
Access and use of this website and the material on it are subject to the Terms and Conditions set forth at
Energy Management Plan: Section One Facilities Lighting Upgrade
National Research Council Canada Institute for Ocean Technology Conseil national de recherches Canada Institut des technologies oc ´eaniques
SR-2009-12
Student Report
Energy Management Plan: Section One Facilities Lighting
Upgrade.
Bartlett, C.
Bartlett, C., 2009. Energy Management Plan: Section One Facilities Lighting Upgrade. St. John's, NL : NRC Institute for Ocean Technology. Student Report, SR-2009-12.
DOCUMENTATION PAGE
REPORT NUMBER
SR-2009-12
NRC REPORT NUMBER DATE
August 2009
REPORT SECURITY CLASSIFICATION
Unclassified DISTRIBUTION Unlimited TITLE AUTHOR(S) Courtney Bartlett
CORPORATE AUTHOR(S)/PERFORMING AGENCY(S)
Institute for Ocean Technology, National Research Council, St. John’s, NL
PUBLICATION
SPONSORING AGENCY(S)
IOT PROJECT NUMBER NRC FILE NUMBER
KEY WORDS
Lighting, energy, inefficient, ergonomics, sensors
PAGES
12, App. A-E
FIGS. TABLES
SUMMARY
The current lighting system at the National Research Council - Institute for Ocean
Technology (NRClOT) is inefficient and causing an increase in energy costs, which raise the cost of energy bills, maintenance and labour. This rising cost is expected to continue to increase in the foreseeable future. NRC-lOT has searched for more efficient products and solutions that will help with the reduction in operating costs. Lighting is recognized
as a major area for economic energy savings.
ADDRESS National Research Council
Institute for Ocean Technology Arctic Avenue, P. O. Box 12093 St. John's, NL A1B 3T5
1+1
National Research Council Conseil national de recherchesCanada Canada
Institute for Ocean
Technology Institut des technologiesoceaniques
Development
&
Implementation of a Lighting
Efficiency Plan
SR-2009-12
Courtney Bartlett
Summary
The following report was based on work completed at the National Research Council - Institute for Ocean Technology (NRC-lOT). The current lighting system at NRC-lOT is inefficient and therefore causing an increase in energy costs. This in turn raises the cost of energy bills, maintenance and labour. The rising cost is expected to continue in the foreseeable future. NRC-lOT has searched for more efficient products and solutions that will help with the reduction in operating costs. Lighting is recognized as a major area for
. .
economic energy savmgs.
The following will be discussed in this report: ergonomics of lighting in offices, problems associated with the current system, savings in energy and cost associated with the new system, the environmental effects of the old and new system, and the reduction in maintenance and labour of the new system. The upgrade will consist of a modern more efficient lighting system that will be installed within a year. Occupancy sensors will be installed and integrated into the lighting circuits of the building. These sensors will turn the lights off when a space is unoccupied for a period of time and will turn these lights on again once the sensor has redetected a person in the area. Also, included in this report are recommendations for the plan to be completed in a timely manor and suggestions for proper implementation.
Methodology
Information for this report was obtained through the NRC-lOT network, which all
employees have access to. Stored on this network is documentation pertaining to specific
projects implemented at lOT, such as pdf and auto-cad drawings, facility project plans, fOlms
and templates. Information was also obtained through Natural Resources Canada Energy
Efficiency documentation. Depending on the topic of discussion, the appropriate personnel
were contacted for guidance and assistance.
Acknowledgments
I would like to thank Mr. Rod Grittiths, Maintenance Supervisor, for answering
questions and providing ongoing support and guidance for the past sixteen weeks. Rod was a
major source of information and contributed his expertise to the Facilities Engineering
SUPP0l1 & Maintenance department at lOT. His guidance and knowledge contributed to the
development of the Lighting Efficiency Plan. He showed consistent determination in
expanding my experience, and most importantly encouraging me to learn through
involvement in changeling projects. This involvement fostered my independent development
Table of Contents
1.0 Introduction
I
2.0 Lighting Efficiency Plan
2
3.0 Current and Proposed Lighting Systems
3
4.0 Construction Phases
5
5.0 Cost Savings
7
6.0 Lighting in Offices
9
7.0 Conclusion
10
8.0 Recommendations
11
9.0 References
12
List ofAppendices
Appendix A
Site Map
Appendix B
Bulb Diameter Comparison
Appendix C
Energy Efficient Lighting Savings Calculator
Appendix D
.Key Plan
1.0 Introduction
The Institute for Ocean Technology (lOT), a branch of the National Research
Council was established in 1985 to provide technical exper1ise in support of Canada's
ocean teclmology industries. The Institute's capability is unique to the nation. No other
organization offers the combination of knowledge, experience and world-class facilities.
lOT conducts ocean engineering research through the modeling of ocean environments,
predicting and improving the performance of marine systems, and developing innovative
technologies that bring benefits to the Canadian marine industry [II.
The Facilities Engineering Support & Maintenance (FESM) department manages
the provision of utilities for the Institute. It provides safe and efficient operations,
maintenance management of buildings, grounds, process systems, and material handling
equipment, maintenance servicing for lab and shop equipment, and project management
services for design, construction and procurement projects.
Due to the large size of lOT's facility and its operations in the ice tank, tow tank
and ocean engineering basin, energy costs soar in the tens of thousands every month.
FESM is assigned the role of planning and implementing an Energy Management Plan to
reduce these costs. Lighting is recognized as a major area for economic energy savings
and is one of the simplest upgrades that can be made. It is for this reason that a lighting
upgrade is chosen as section one of the energy management plan.
2.0 Lighting Efficiency Plan
lOT is composed of several thousand square feet of lighted area at its facility in St. John's (Refer to Appendix A for Site Map). Employment consists of over one hundred lOT staff and another fifty contractors. Since the facility was built in 1986, there has been no lighting retrofit. The current lighting system is inefficient, causing an increase in energy consumption; which therefore raises the cost of energy bills, maintenance and labour. This rising cost is expected to continue to increase in the foreseeable future. lOT has searched for more efficient products and solutions that will help with the reduction in operating costs. Objectives of this project are to reduce energy consumption and lower energy bills, reduce maintenance and labour, improve quality of lighting, consume less electricity and reduce harmful emissions associated with power generation.
The first step associated with the lighting upgrade is to divide the facility into separate construction phases, allowing each area's project management to be less complex. The second step is to develop a more comprehensive understanding of the current lighting system so it can be assessed. Once problems associated with the current system are determined, the third step it to establish a more efficient alternate method of lighting. The fourth step is to bring professionals, Blair Davis from B. Davis Agencies LTD. and Gus Gallant from McLoughlan Supplies Ltd., into the facility to complete tours of each phase area and decide exactly what supplies are needed for upgrade. The final step is the installation of supplies in each phase area.