• Aucun résultat trouvé

Waste Water Collection Pipe Network (1) Works and the Layout(1) Works and the Layout

Dans le document Td corrigé DOC - World Bank Documents pdf (Page 54-63)

2. Project Overview

2.4 Project Components

2.5.1 Waste Water Collection Pipe Network (1) Works and the Layout(1) Works and the Layout

Waste water collection pipe network will cover areas of Xichuan River, Beichuan River and Beichuan Zone(Area).

1) Layout of Waste Water Collection Pipeline on South Bank of Xichuan River It is planned in the Project to arrange a main waste water collection pipe on the south bank of the Xichuan River from Yangjiawan Village to Duoba, which will collect all the waste water on the south bank of the Xichuan River from Duoba to Yangjiawan Village, which will flow into the existing downstream waste water collection pipes and finally flow into the No.4 WWTP for treatment.

Figure 2.5-3 Layout of Waste Water Collection Pipeline on South Bank of Xichuan River

Gravel Road Irrigated Land Woodland

Figure 2.5-4 Waste Water Collection System on the South Bank

of Xichuan River Figure 2.5-5 Current Status of Areas across/along Which the Pipeline on South Bank of Xichuan River Is Planned 1: Main combined waste water collection pipe; 2: Main interception

pipe; 3: Overflow well; 4: The fourth WWTP; 5: Outlet; 6: Overflow outlet; 7: Sedimentation well

No.4 WWTP under construction

Planned Waste Water Pipe Existiing Waste Water Pipe

Combined system will be adopted for short term for waste water collection pipeline along Xichuan and Beichuan rivers. Along with completion of road construction along both banks of the rivers in the long run and rainwater collection system and preliminary rainwater treatment system put into place gradually, the combined system will be changed to separate system consecutively. Such arrangement for waste water collection pipe system also couples with construction and development of waste water treatment plants in the short and long terms.

(1) Waste water collection pipes are designed based on needs of 2030, since sewage amount in the short term will be relatively small, combined system can make better use of the available pipe space. Along with increase of sewage from the service areas, the combined system can be gradually changed to separate system, and the current pipe diameter can still meet sewage collection requirement then.

(2) Sewage from both banks of Xichuan River and Beichuan River will flow into No.4 and No.5 WWTPs after being collected. At present, construction of both WWTPs are based on a treatment capacity of 30 thousand m3/d for the short term, while it is predicted that the flowing-in sewage will be only around 23 thousand m3/d in the near future. Therefore, use of combined system can meet the treatment requirement of combined waste water, and ensure better use of capacity of the WWTPs.

Since the road along Xichuan River is not yet constructed, the waste water collection pipeline will be installed along the existing gravel road or in the irrigated land or woodland.

2) Layout of Waste Water Pipeline on Both Banks of Beichuan River

It is planned in the Project to arrange main waste water collection pipe along the Beichuan River on both banks from Ningda Road toll-gate to Datong Waste Water Treatment Plant, with diameters ranging from DN800 to DN1000.

Combined waste water collection system will be adopted in the short term and it will be changed gradually to separate system when the road system and rainwater discharge system are completed in the area.

Since the roads along Beichuan River are not yet constructed, the waste water collection pipeline will be installed along the existing gravel road or in the irrigated land or woodland.

3) Layout of Waste Water Pipeline in Beichuan Zone

As the land relief in the Beichuan Zone is high in the north and the west and low in the south and the east, the layout is made in accordance with the road directions:

the master main sewer (waste water pipe) is arranged along the Tiedong Road which is a south-north road, the main sewers are arranged along Binghe Road which is a south-north road, and branch sewers (branch waste water pipes) are arranged along other east-west roads. In this zone, the waste water will be collected into the main interception pipe of the Beichuan River, flowing into the main interception pipe on the north bank of the Huangshui River and then entering into the No.3 WWTP for treatment.

Figure 2.5-6 Layout of Pipeline along Both Banks of Beichuan River

Gravel Road Irrigated Land wood Land

Figure 2.5-7 Waste Water Collection System along Both Banks of Beichuan River Figure 2.5-8 Current Status of Areas across/along Which the Pipeline on Both Banks of Xichuan River Is Planned 1: Main combined waste water collection pipe; 2: Main

interception pipe; 3: Overflow well; 4: No.5 WWTP; 5: Outlet;

6: Overflow outlet; 7 : Sedimentation well

Planned Waste Water Pipe Existingd Waste Water Pipe

No.5 WWTP under construction Waste Water Pipe under construction

Figure 2.5-9 Layout of Wastewater Pipes in Beichuan Area

Figure 2.5-10 Illustration of Altitudes of Beichuan Area Figure 2.5-11 Current Status of Site

(2) Prediction of Waste Water Amount and the Transfer Scheme

Results of predicted waste water collection amounts in 2030 are included in the following table.

Table 2.5-2 Summary of Predicted Waste Water Collections in 2030

No. Areas

Population Served

(104 persons)

Service Area

(ha)

Waste Water Collected

(104 m3/d) Discharged to 1 South Bank of

Xichuan River 17.2 1442 4.36 The Fourth WWTP

2 East Bank of

Beichuan River 2.45 940 0.80 The Fifth WWTP

3 West Bank of

Beichuan River 5.90 3800 1.64 The Fifth WWTP

4 Beichuan Zone 4.00 290 1.10 The Third WWTP

(3) Type of Foundation for the Pipeline

For the reinforced concrete sewer pipe, 120º plain concrete foundation will be used, and C35 concrete is the casting standard. The foundation is illustrated as follows.

Figure 2.5-12 Illustration of Foundation of Pipeline Table 2.5-3 Dimensions of Plain Concrete Foundation

DN Thickness of

Pipe Wall a Dimensions of the FoundationB C1 C2 Slope

300 40 80 540 80 95 1:0.75

400 47 100 694 100 123 1:0.75

600 60 100 920 100 180 1:0.75

800 80 120 1200 120 240 1:0.75

1000 100 150 1500 150 300 1:0.75

(4) Main Quantities

The main quantities of the urban waste water collection pipe network are shown in Tables 2.5-4 through to 10.

1) Xichuan River Waste Water Collection Pipeline(Yangjiawan village-Duoba)

Backfilling and compaction by layer, 100-200 mm per layer

C35 Concrete Ground Elevation

Table 2.5-4 Pipe Material and Quantities of Well Chambers for Xichuan River

No. Description Specification material Unit Quantity Remarks

1 Reinforced concrete

pipe DN800 Reinforced

concrete m 2600 Main pipe

2 Reinforced concrete

pipe DN1000 Reinforced

concrete m 10920 Main pipe

3 Reinforced concrete

pipe DN400 Reinforced

concrete m 2480 Branch pipe

4 Rectangular waste

water pipe manhole 1100X1100 Reinforced

concrete No. 65

5 Rectangular waste

water pipe manhole 1100X1300 Reinforced

concrete No. 218 In branch pipe

6 Circular waste water

pipe Manhole Φ1000 Brick No. 82 In branch pipe

7 Sedimentation Well Φ1250 Reinforced

Concrete No. 7 In branch pipe

8 Overflow Well 1650x1650 Reinforced

Concrete No. 7 In branch pipe

Table 2.5-5 Activities Needed to Be Accomplished before Construction of the Pipeline

No. Activities Unit Quantity Remark

1 Construction of

Temporary Roads m2 18830 For pipeline located in flood land, irrigated land areas, 5380m 2 Compensation to

Green Crops m2 40140 For pipeline located in irrigated land, 4460m

3 Restoration of

gravel road surface m2 13360 For pipeline located along gravel road, 3340m

4 Land Acquisition

for Manholes mu 0.7 For manholes located in irrigation land areas

(90 such manholes) 5 Compensation for

tree seedlings No. 9600 For pipeline located in the woodland, 4800m

6 Stone Masonry m3 3750 River channel slope protection

2) Waste Water Collection Pipeline along Both Banks of Beichuan River (Ningda Road toll-gate-Datong WWTP)

Table 2.5-6 Pipe Material and Quantities of Well Chambers for East Bank of Beichuan River

No. Description Specification material Unit Quantity Remarks Remarks

1 Reinforced concrete

pipe DN800 Reinforced

concrete m 2665 Main pipe

Main pipe 2 Reinforced concrete

pipe DN1000 Reinforced

concrete m 12500 Main pipe

Main pipe 3 Reinforced concrete

pipe DN400 Reinforced

concrete m 1835 Branch pipe Main pipe

4 Rectangular waste

water pipe manhole 1100X1100 Reinforced

concrete No. 66 Branch pipe

5 Rectangular waste

water pipe manhole 1100X1300 Reinforced

concrete No. 278 In branch

pipe 6 Circular waste water

pipe Manhole Φ1000 Brick No. 52 In branch

pipe

7 Sedimentation Well Φ1250 Reinforced

Concrete No. 9 In branch

pipe

8 Overflow Well 1650x1650 Reinforced No. 9 In branch To be provided

Concrete pipe in branch pipes

Table 2.5-7 Activities Needed to Be Accomplished before Construction of the Pipeline on East Bank of Beichuan River

No. Activities Unit Quantity Remark

1 Construction of

Temporary Roads m2 20090 For pipeline located in flood land, irrigated land areas, 5740m 2 Compensation to

Green Crops m2 30600x1.5 For pipeline located in irrigated land, 5100m

3 Restoration of

gravel road surface m2 13360 For pipeline located along gravel road, 3340m

4 Land Acquisition

for Manholes mu 540 For manholes located in irrigation land areas

(104 such manholes) 5 Compensation for

tree seedlings No. 8480 For pipeline located in the woodland, 4240m

Table 2.5-8 Pipe Material and Quantities of Well Chambers for West Bank of Beichuan River

No. Description Specification Material Unit Quantity Remarks

1 Reinforced concrete

pipe DN800 Reinforced

concrete m 2665 Main pipe

2 Reinforced concrete

pipe DN1000 Reinforced

concrete m 12500 Main pipe

3 Reinforced concrete

pipe DN400 HDPE m 1835 Main pipe

4 Manhole 1100X1100 Reinforced

concrete No. 35

5 Manhole 1100X1300 Reinforced

concrete No.

275

6 Circular Manhole Φ1000 Brick No. 52 In branch pipe

7 Sedimentation Well Φ1250 Reinforced

concrete No.

12 In branch pipe

8 Overflow Well 1650x1650 Reinforced

concrete No.

12 In branch pipe

Table 2.5-9 Activities Needed to Be Accomplished before Construction of the Pipeline on West Bank of Beichuan River

No. Activities Unit Quantity Remark

1 Construction of

Temporary Roads m2 23905 For pipeline located in flood land, irrigated land areas, 6830m 2 Compensation to

Green Crops m2 35820x1.5 For pipeline located in irrigated land, 5970m

3 Restoration of

gravel road surface m2 18860 For pipeline located along gravel road, 4715m

4 Land Acquisition

for Manholes mu 624 For manholes located in irrigation land areas

(120 such manholes) 5 Compensation for

tree seedlings No. 4040 For pipeline located in the woodland, 2020m

Dans le document Td corrigé DOC - World Bank Documents pdf (Page 54-63)