Dynamic Lot Sizing Detailed Calculations

Period 1 2 3 4 5 6 7 8 9 10

Demand 10 15 12 16 15 12 18 14 22 16

Order cost = $150.

Carrying cost = $2 per item per period (based on average).

Part Period Balance (PPB)

Alternative Order

Cost Carrying

Cost Remarks

Order 10 to cover the needs of period 1 150 10 Continue until carrying costs pass order cost

Order 25 to cover the needs of periods 1 and 2 150 55 Continue until carrying costs pass order cost

Order 37 to cover the needs of periods 1, 2 and 3 150 115 Continue until carrying costs pass order cost

Order 53 to cover the needs of periods 1, 2, 3 and 4 150 227 Stop as carrying costs are larger than order cost

Decision: since 115 is closer to 150 than 227 is, order 37 to cover the needs of periods 1, 2 and 3 Order 16 to cover the needs of period 4 150 16 Continue until carrying costs

pass order cost

Order 31 to cover the needs of periods 4 and 5 150 61 Continue until carrying costs pass order cost

Order 43 to cover the needs of periods 4, 5 and 6 150 121 Continue until carrying costs pass order cost

Order 61 to cover the needs of periods 4, 5, 6, and 7 150 247 Stop as carrying costs are larger than order cost

Decision: since 121 is closer to 150 than 247 is, order 43 to cover the needs of periods 4, 5 and 6 Order 18 to cover the needs of period 7 150 18 Continue until carrying costs

pass order cost

Order 32 to cover the needs of periods 7 and 8 150 60 Continue until carrying costs pass order cost

Order 54 to cover the needs of periods 7, 8, and 9 150 170 Stop as carrying costs are larger than order cost

Decision: since 170 is closer to 150 than 60 is, order 54 to cover the needs of periods 7, 8, and 9.

Since only period 10 remains in the planning horizon, order the needs of that period.

Total cost = 150 + 115 + 150 +121 + 150 + 170 + 150 + 16 = $1,022.

(2)

Silver-Meal (SM)

Alternative Order

Cost

Carrying Cost

Total Cost per period

Remarks

Order 10 to cover the needs of period 1 150 10 160.00 Continue

Order 25 to cover the needs of periods 1 and 2 150 55 102.50 Continue Order 37 to cover the needs of periods 1, 2 and 3 150 115 88.33 Continue Order 53 to cover the needs of periods 1, 2, 3 and 4 150 227 94.25 Stop

Decision: since 88.33 is the minimum, order 37 to cover the needs of periods 1, 2, and 3

Order 16 to cover the needs of period 4 150 16 166 Continue

Order 31 to cover the needs of periods 4 and 5 150 61 105.5 Continue Order 43 to cover the needs of periods 4, 5 and 6 150 121 90.33 Continue Order 61 to cover the needs of periods 4, 5, 6, and 7 150 247 99.25 Stop

Decision: since 90.33 is the minimum, order 43 to cover the needs of periods 4, 5, and 6

Order 18 to cover the needs of period 7 150 18 168 Continue

Order 32 to cover the needs of periods 7 and 8 150 60 105 Continue

Order 54 to cover the needs of periods 7, 8, and 9 150 170 106.67 Stop Decision: since 105 is the minimum, order 32 to cover the needs of periods 7 and 8

Order 22 to cover the needs of period 9 150 22 172 Continue

Order 38 to cover the needs of periods 9 and 10 150 70 110 Stop

Decision: since 110 is the minimum and no more periods to go, order 38 to cover the needs of periods 9 and 10

Total cost = 150 + 115 + 150 +121 + 150 + 60 + 150 + 70 = $966.

Références

Documents relatifs

Attention, ce ne sont pas des fractions rationnelles !!! Il faut factoriser par le terme dominant numérateur, dénominateur, puis simplifier la fraction.. On obtient comme

Ce module a pour objectif d'amener les étudiants à l'état de la connaissance sur les bases de données et de présenter les méthodes et techniques pour la conception, la réalisation

Le moteur fonctionne en charge ( <i> = 0 ) sous tension constante. Pour limiter cette variation de vitesse, on utilise un dispositif de régulation de vitesse dont le

C'est monstrueusement dangereux et ca embete (ce qui est un mot charmant et delicat) les automobilistes. J'ai mal au pied. Je ne sais plus comment me mettre. Ai eu grosse crise

Réalisation d’une fonction logique à l’aide de portes NAND exclusivement.. TD

98 Je résume ici l'analyse proposée par Spinoza dans la deuxième partie de son Éthique (1677), qu'il conclut en déclarant que si l'on a bien compris comment une représentation se

Unité d’enseignement : UEF 3.1.1 Matière : Hydraulique générale II VHS: 45h00 (cours: 1h30, TD: 1h30) Crédits : 4. Coefficient

Indiquer sur votre copie le nombre de transformateurs et la longueur totale des câbles pour chaque solution.. La structure avec l’alimentation séparée nécessite 8 transformateurs