PREVENTIVE AND EMERGENCY
PREVENTIVE AND EMERGENCY
TRANSIENT STABILITY CONTROL
TRANSIENT STABILITY CONTROL
Damien Ernst, Daniel Ruiz
Damien Ernst, Daniel Ruiz--VegaVega and Mania Pavella
Action taken before the contingency inception
Preventive control
Dangerous operating condition; risk of instability if a severe contingency occurs.
Emergency control
Action taken after the contingency inception
STATEMENT OF THE PROBLEM
Preventive and emergency control
Preventive and emergency control
features
features
Preventive control
Preventive control
:: ■■ Designed by offDesigned by off--line simulationsline simulations ■
■ Modifies the operating conditions of the systemModifies the operating conditions of the system ■
■ Costs money even if contingency does not Costs money even if contingency does not occur
occur
Emergency control
Emergency control
:: ■■ Triggered only if contingency occursTriggered only if contingency occurs ■
EXAMPLE OF EMERGENCY AND
EXAMPLE OF EMERGENCY AND
PREVENTIVE CONTROLS
PREVENTIVE CONTROLS
■
■ Test network : 88Test network : 88--machine EPRI test system Cmachine EPRI test system C ■
■ Only transient stability taken into accountOnly transient stability taken into account ■
■ Contingency considered here : 3Contingency considered here : 3--ΦΦ shortshort- -circuit cleared after 100 ms by opening of a
circuit cleared after 100 ms by opening of a
line.
SIME approach to transient stability
SIME approach to transient stability
The
The OMIB OMIB ((OOne ne MMachine achine IInfinite nfinite BBus):us): ■
■ reduces the multimachine power system dimensionsreduces the multimachine power system dimensions ■
■ assesses transient stability using the equal area criterion assesses transient stability using the equal area criterion ■
P
η
Preventive control
Preventive control
■
■ 739 MW (2 %) 739 MW (2 %) reschedulingrescheduling is enough to is enough to stabilize the system.
stabilize the system.
■
■ The same procedure carried out on many The same procedure carried out on many contingencies leads to on
contingencies leads to on--line preventive line preventive TSA&C. TSA&C. 23,884 1.072 24,258 24,623 -1.044
Power System
Power System
Unstable Case
Is the margin negative ?
Stability Margin Critical Machines
Yes
Design of Control Action Find appropriate action
to stabilize the system
Real Time Measurements
Applying the emergency action
3 machines are actually shed Fault cleared by tripping line
A fault is applied
Loss of synchronism is detected
3 machines are to be shed
The system goes back to synchronism
t=565 ms
t=415 ms t=375 ms t=100 ms
Variation of control size vs control time
Variation of control size vs control time
■
■ Size of control increases with the Size of control increases with the ““time to time to control
control””.. ■
■ Corrective action should be triggered as soon as Corrective action should be triggered as soon as possible.
Conclusions
Conclusions
■
■ SIME provides efficient techniques for both SIME provides efficient techniques for both preventive and emergency transient stability
preventive and emergency transient stability
control.
control.
■
■ Technically emergency control is more difficult Technically emergency control is more difficult to achieve; but it opens avenues to new
to achieve; but it opens avenues to new
solutions for security problems in a deregulated
solutions for security problems in a deregulated
market.
market.
■
■ Emergency control is not meant to replace Emergency control is not meant to replace
preventive control but rather to complement it.