• Aucun résultat trouvé

1. Nuclear thermal capacity (P(th), MW(th)) Reactor nuclear thermal capacity

(as derived from a heat balance measurement on the reactor primary coolant system).

2. Maximum electrical capacity of a nuclear station (P

g

or P

n

, MW(e))

The 'maximum capacity of a nuclear station' is the maximum power that could be maintained or is authorized to be maintained throughout a period of continuous operation, in practice 15 hours or longer. It is specified that this value must remain constant for a given unit unless, following permanent modification, or a new permanent authorization, the management of the undertaking decides to amend the original value.

Electrical capacity may be gross of net:

– The gross capacity (P

g

, MW(e)) is deemed to be measured at the output terminals of all generator sets in the station; it includes therefore the power taken by the station auxiliaries and losses in transformers that are considered integral parts of the station.

– The net capacity (P

n

, MW(e)), indicating the maximum power that can be supplied, is measured at the station outlet terminals, i.e. after deducting the power taken by station auxiliaries and the losses in the transformers that are considered integral parts of the station.

It is recognized that the maximum capacity may be set by an authorized maximum thermal capacity and in these cases the 'reference' maximum net electrical capacities corresponding to the authorized maximum thermal capacity should be used for simplicity in the calculations.

3. Reference period (T, hours)

For units in power ascension at the end of the period, the clock hours from the beginning of the period or the first electrical production, whichever comes last, to the end of the period.

For units in commercial operation at the end of the period, the clock hours from the beginning of the period or of commercial operation, whichever comes last, to the end of the period or permanent shutdown, whichever comes first.

4. On-line hours (t, hours)

The total clock hours in the reference period during which the unit operated with breakers closed to the station bus.

5. Maximum net energy produced (E

m,

MW(e)·h)

Net electrical energy which would have been produced at maximum capacity

under continuous operation during the whole of the reference period.

Electrical output of the unit during the reference period as measured at the station outlet terminals, i.e. after deducting the electrical energy taken by station auxiliaries and the losses in the transformers that are considered integral parts of the station. If this quantity is less than zero, zero is reported.

7. Load factor (LF, %) E 100

= E LF

m

× E = net energy produced ((MW(e)·h)

E

m

= maximum net energy produced (MW(e)·h) The load factor for a unit or station for a given period of time is the ratio of the energy that it produced during the period considered to the energy that it could have produced at maximum capacity under continuous operation during the whole of that period.

8. Operation factor (OF, %) T 100

= t

OF × t = number of hours on-line (h) (MW(e)·h) T = number of hours in the reference period (h)0 The operation factor is the ratio between the number of hours the unit or station was on-line and the total number of hours in the reference period.

9. Available capacity (P, MW)

The available capacity at a given moment is the maximum capacity at which the station can be or is authorized to be operated at a continuous rating under the prevailing conditions assuming unlimited transmission facilities.

10. Energy loss (EL, MW(e)·h)

Energy loss is the energy which could have been produced during the reference period by the unavailable capacity; it is categorized into three types – ELP, ELU and ELX – i.e. energy loss planned, energy loss unplanned due to causes in the plant and energy loss unplanned due to causes external to the plant.

11. Unavailability

Unavailability means that the available capacity is lower than the maximum capacity. Unavailability is classified as planned if it is foreseen at least 1–3 months in advance, generally at the time when the annual overhaul programme is established, and if the beginning of the unavailability period can be largely controlled and deferred by management. Unavailability is classified as unplanned when it is due either to causes in the plant or causes external to the plant. Power plant operation at lower than maximum capacity because of lower demand from the grid (other than stretch-out operations) but available to operate at the maximum capacity, does not constitute unavailability, either planned or unplanned.

12. Energy unavailability (EUF, %) E 100

= EL EUF

m

×

20

could have been produced during this period by a capacity equal to the unavailable capacity P and the energy E

m

that could have been produced during the same period by the maximum capacity.

The energy unavailability factor EUF over a specified period can be divided into:

PUF = planned unavailability factor

UUF = unplanned unavailability factor due to causes in the plant

XUF = unplanned unavailability factor due to causes external to the plant.

13. Energy availability factor (EAF, %) EAF = 100 – EUF

14. Unit capability factor (UCF, %)

UCF = (REG - PEL - UEL) x 100 % REG

15. Construction start

Date when first major placing of concrete, usually for the base mat of the reactor building, is done.

16. First criticality

Date when the reactor is made critical for the first time.

17. Grid connection

Date when the plant is first connected to the electrical grid for supply of power.

18. Commercial operation

Date when the plant is handed over by the contractors to the owner and declared officially to be in commercial operation.

19. Shutdown

Date when the plant is officially declared shut down by the owner and taken out of operation permanently.

20. Significant outages

A significant outage is a power reduction resulting in a loss of energy corresponding to at least ten hours of continuous operation at maximum capacity.

(When reported to the IAEA, outages smaller than significant ones are also included in the report.)

21. Outage duration (hours)

The total clock hours of the outage measured from the beginning of the reference period or the outage, whichever comes last, to the end of the reference period or the outage, whichever comes first.

22. Factors refer to the plants which were in commercial operation during the whole of the reference period.

23. Cumulative factors are given for the plants which were in commercial operation

during full calendar years.

24. A blank and three periods (...), if used in tables, denote information that is not applicable or not available, respectively.

25. Types of outages

Outages or unavailabilities are categorized as full or partial. The outage/unavailability is considered full when net power is reduced to zero per cent. The outage/unavailability is considered partial when the available capacity is lower than the maximum net capacity. The following abbreviations are used to indicate the type of outage.

First digit:

P = planned outage U = unplanned outage

X = outage due to causes not attributable to the plant itself.

Examples:

– shortage of fuel – shortage of water

– special testing caused by experience at other plants – requirements of manufacturers, especially for new plants – staff shortages and strikes

– regulatory requirements.

Second digit:

F = full outage P = partial outage.

Third digit:

1 = Controlled shutdown or load reduction that could be deferred but had to be performed earlier than four weeks after the cause occurred or before the next refuelling outage, whatever comes first

2 = Controlled shutdown or load reduction that had to be performed in the next 24 hours after the cause occurred

3 = Outage extension

4 = Reactor scram, automatic 5 = Reactor scram, manual

26. Main causes of outages/unavailabilities (full or partial) (A) Plant equipment failure

(B) Refuelling without a maintenance

(C) Inspection, maintenance or repair combined with refuelling (D) Inspection, maintenance or repair without refuelling

(E) Testing of plant systems or components

(F) Major back-fitting, refurbishment or upgrading activities with refuelling (G) Major back-fitting, refurbishment or upgrading activities without refuelling (H) Nuclear regulatory requirements

(J) Grid failure or grid unavailability

(K) Load-following (frequency control, reserve shutdown due to reduced energy demand)

(L) Human factor related

(M) Governmental requirements or Court decisions

(N) Environmental conditions (flood, storm, lightning, lack of cooling water due to dry weather, cooling water temperature limits etc.)

(P) Fire

22

payments from customers, disputes in fuel industries, fuel-rationing, labour strike outside the plant

1

, spare part delivery problems etc.)

(S) Fuel management limitation (including high flux tilt, stretch out or coast-down operation)

(T) Offsite heat distribution system unavailability

(U) Security and access control and other preventive shutdown due to external threats

(Z) Others

27. Plant systems affected Nuclear System

11 Reactor and accessories Includes:

Reactor vessel and main shielding Reactor core (including fuel assemblies0

Reactor internals (including steam separators/dryers) Auxiliary shielding and heat insulation

Moderator and auxiliaries (PHWR) Annulus gas system (PHWR/RBMK) Non of them above system

12 Reactor instrumentation and control (I&C) systems Includes:

Control and safety rods and drives

Neutron monitoring (in-core plus external) Reactor instrumentation (except neutron) Reactor control system

Reactor protection system Process computer

Reactor recirculation control (BWR) Non of them above system

13 Reactor Auxiliary Systems Includes:

Primary coolant treatment and cleanup system (BWR and GCR) Chemical and volume control system (PWR)

Residual heat removal system (including heat exchangers) Component cooling system

Gaseous, liquid and solid radwaste treatment

Nuclear building ventilation and containment inerting systems

Nuclear equipment venting and drainage system (including room floor drainage) Borated or refuelling water storage system

CO

2

injection and storage system (GCR) Sodium heating system (FBR)

Primary pump oil system (including RCP or make-up pump oil) D

2

O leakage collection and dryer system (PHWR)

Essential auxiliary system (GCR)

Non of them above system

Includes:

Emergency core cooling systems (including accumulators and core spray system) High pressure safety injection and emergency poisoning system

Auxiliary and emergency feedwater system Containment spray system (active)

Containment pressure suppression system (passive)

Containment isolation system (isolation valves, doors, locks and penetrations) Containment structures

Fire protection system None of the above systems 15 Reactor cooling system Includes:

Reactor coolant pumps/blowers and drives

Reactor coolant piping (including associated valves)

Reactor coolant safety and relief valves (including relief tank) Reactor coolant pressure control system

Main steam piping and isolation valves (BWR) None of the above systems

16 Steam generation system Includes:

Steam generator (PWR), boiler (PHWR, AGR), steam drum vessel (RBMK, BWR)

Steam generator blow-down system

Steam drum level control system (RBMK, BWR) None of the above systems

17 Safety I&C systems (excluding reactor I&C) Includes:

Engineered safeguard feature actuation system Fire detection system

Containment isolation function

Main steam/feedwater isolation function

Main steam pressure emergency control system (turbine bypass and steam dump valve control)

Failed fuel detection system (DN monitoring system for PHWR) RCS integrity monitoring system (RBMK)

None of the above systems

Fuel and Refuelling System

21 Fuel Handling and Storage Facilities Includes:

On-power refuelling machine Fuel transfer system

Storage facilities, including treatment plant and final loading and cask handling facilities

None of the above systems Secondary Plant System

31 Turbine and auxiliaries

24

Turbine

Moisture separator and re-heater Control valves and turbine stop valves Turbine control valves and stop valves Main condenser (including vacuum system) Turbine by-pass valves

Turbine auxiliaries (lubricating oil, gland steam, steam extraction) Turbine control and protection system

None of the above systems

32 Feedwater and Main Steam System Includes:

Main steam piping and valves Main steam safety and relief valves

Feedwater system (including feedwater tank, piping, pumps and heaters) Condensate system (including condensate pumps, piping and heaters) Condensate treatment system

None of the above systems 33 Circulating water system Includes:

Circulating water system (pumps and piping/ducts excluding heat sink system) Cooling towers / heat sink system

Emergency ultimate heat sink system None of the above systems

34 Miscellaneous systems Includes:

Compressed air (essential and non-essential / high-pressure and low-pressure) Gas storage, supply and cleanup systems (nitrogen, hydrogen, carbon dioxide etc.)

Service water / process water supply system (including water treatment) Demineralized water supply system (including water treatment)

Auxiliary steam supply system (including boilers and pressure control equipment)

Non-nuclear area ventilation (including main control room) Chilled water supply system

Chemical additive injection and makeup systems Non-nuclear equipment venting and drainage system Communication system

None of the above systems 35 All other I&C systems

Includes:

Plant process monitoring systems (excluding process computer) Leak monitoring systems

Alarm annunciation system Plant radiation monitoring system Plant process control systems None of the above systems Electrical System

41 Main generator

Includes:

Generator and exciter (including generator output breaker) Sealing oil system

Rotor cooling gas system 42 Electrical power supply systems Includes:

Main transformers

Unit self-consumption transformers (station, auxiliary, house reserve etc.) Vital AC and DC plant power supply systems (medium and low voltage) Non-vital AC plant power supply system (medium and low voltage)

Emergency power generation system (e.g. emergency diesel generator and auxiliaries)

Power supply system logics (including load shed logic, emergency bus transfer logic, load sequencer logic, breaker trip logic etc.)

Plant switchyard equipment None of the above systems

26

0 2000 4000 6000 8000 10000

1958 1963 1968 1973 1978 1983 1988 1993 1998 2003

Cumulative Reactor-Years

The future potential

Data unavailable to the IAEA

Data available in IAEA PRIS

Figure 2 — Lifetime Energy Availability Factors up to 2003

(only reactors with capacity greater than 100 MW(e) and with more than one year of commercial operation)

Figure 3 — Reactors with High Availability Factors

13

42

3 0 0 2 3

1

20

72

61

13

0 0

20 40 60 80

< 30% 30 – 35% 35 – 40% 40 – 45% 45 – 50% 50 – 55% 55 – 60% 60 – 65% 65 – 70% 70 – 75% 75 – 80% 80 – 85% 85 – 90% 90 – 95% > 95%

Energy Availability Factor Range

Number of Reactors

0 20 40 60 80 100

1986 1988 1990 1992 1994 1996 1998 2000 2002

% of Reactors

70 – 79% 80 – 89% 90 – 100%

28

Figure 4 — Average Energy Availability Factors

79

81 82 83 84

81

73

75 74

72 73 74 74 74

76

79 78 77

0 10 20 30 40 50 60 70 80 90

1986 1988 1990 1992 1994 1996 1998 2000 2002

Energy Availability Factor (%)

Figure 5 — Number of Reactors in Operation (as of 1 January 2004)

Note: There were 6 reactors in operation in Taiwan, China.

Figure 6 — Number of Reactors by Age (as of 1 January 2004)

59 KOREA RP GERMANY CZECH R.

SLOVAKIA

Number of Reactors

2

Reactor Age (years)

Number of Reactors

30

5. ABBREVIATIONS

COUNTRY CODES

AM ARMENIA AR ARGENTINA BE BELGIUM BG BULGARIA BR BRAZIL CA CANADA CH SWITZERLAND CN CHINA

CZ CZECH REPUBLIC

DE GERMANY ES SPAIN FI FINLAND FR FRANCE

GB UNITED KINGDOM

HU HUNGARY IN INDIA JP JAPAN KR KOREA, REPUBLIC OF

KZ KAZAKHSTAN LT LITHUANIA, REPUBLIC OF MX MEXICO NL NETHERLANDS PK PAKISTAN RO ROMANIA

RU RUSSIAN FEDERATION

SE SWEDEN SI SLOVENIA

SK SLOVAK REPUBLIC

TW TAIWAN, CHINA

UA UKRAINE US UNITED STATES OF AMERICA

ZA SOUTH AFRICA

REACTOR TYPES

ABWR Advanced Boiling Light-Water-Cooled and Moderated Reactor AGR Advanced Gas-Cooled, Graphite-Moderated Reactor BWR Boiling Light-Water-Cooled and Moderated Reactor FBR Fast Breeder Reactor

GCR Gas-Cooled, Graphite-Moderated Reactor

HTGR High-Temperature Gas-Cooled, Graphite-Moderated Reactor HWGCR Heavy-Water-Moderated, Gas-Cooled Reactor

HWLWR Heavy-Water-Moderated, Boiling Light-Water-Cooled Reactor LWGR Light-Water-Cooled, Graphite-Moderated Reactor

PHWR Pressurized Heavy-Water-Moderated and Cooled Reactor PWR Pressurized Light-Water-Moderated and Cooled Reactor SGHWR Steam-Generating Heavy-Water Reactor

WWER Water Cooled Water Moderated Power Reactor

OPERATORS

AMEREN AMEREN AMERGEN AMERGEN ENERGY CO.

ANAV ASOCIACION NUCLEAR ASCO-VANDELLOS A.I.E.

(ENDESA/ID)

ANPP ARIZONA NUCLEAR POWER PROJECT

BE BRITISH ENERGY

BKAB BARSEBECK KRAFT AB BKW BKW ENERGIE AG

BNFL BRITISH NUCLEAR FUELS PLC

BRUCEPOW BRUCE POWER

CEA/EDF COMMISSARIAT A L'ENERGIE ATOMIQUE / ELECTRICITE DE FRANCE

CEZ CZECH POWER COMPANY , CEZ A.S.

CFE COMISION FEDERAL DE ELECTRICIDAD

CHUGOKU CHUGOKU ELECTRIC POWER CO.

CNAT CENTRALES NUCLEARES ALMARAZ- TRILLO(ID/UFG/ENDESA/HC/NUCLENOR ) CONST CONSTELLATION NUCLEAR GROUP DETED DETROIT EDISON CO.

DOMIN DOMINION VIRGINIA POWER DUKE DUKE POWER CO.

EBO ELECTROSTATION BOHUNICE

EDF ELECTRICITE DE FRANCE

ELECTRAB ELECTRABEL M. V. NUCLEAIRE PRODUKTIE ELETRONU ELETROBRAS TERMONUCLEAR SA –

ELETRONUCLEAR

EMO ELECTROSTATION MOCHOVCE

EnBW ENBW KRAFTWERK AG

ENERGYNW ENERGY NORTWEST

ENTERGY ENTERGY NUCLEAR

EON EON KERNKRAFT GES.M.B.H

EPZ N.V. ELEKTRICITEITS-PRODUKTIEMAATSCHAPPIJ ZUID-NEDERLAND

ESKOM ESKOM EXELON EXELON NUCLEAR CO.

FENOC FIRST ENERGY NUCLEAR OPERATING CO.

FKA FORSMARK KRAFTGRUPP AB

FORTUMPH FORTUM POWER AND HEAT OY (FORMER IVO) FPL FLORIDA POWER & LIGHT CO.

GNPJVC GUANDONG NUCLEAR POWER JOINT VENTURE COMPANY LIMITED(GNPJVC)

HEPCO HOKKAIDO ELECTRIC POWER CO.

HEW HAMBURGISCHE ELEKTRIZITAETSWERKE

HOKURIKU HOKURIKU ELECTRIC POWER CO.

HQ HYDRO QUEBEC

ID IBERDROLA, S.A.

IMPCO INDIANA MICHIGAN POWER CO.

INPP IGNALINA NUCLEAR POWER PLANT JAPCO JAPAN ATOMIC POWER CO.

JNC JAPAN NUCLEAR CYCLE DEVELOPEMENT INSTITUTE JSC JOINT STOCK COMPANY ARMENIA NPP

KEPCO KANSAI ELECTRIC POWER CO.

KHNP KOREA HYDRO AND NUCLEAR POWER CO.

KKG KERNKRAFTWERK GOESGEN-DAENIKEN AG

KKL KERNKRAFTWERK LEIBSTADT

KYUSHU KYUSHU ELECTRIC POWER CO.

LANPC LINGAO NUCLEAR POWER COMPANY LTD.

NASA NUCLEOELECTRICA ARGENTINA S.A.

NBEPC NEW BRUNSWICK ELECTRIC POWER COMMISSION NEC NATIONAL ELECTRICITY COMPANY, BRANCH NPP-

KOZLODUY

NEK NUKLEARNA ELEKTRARNA KRSKO

NNEGC NATIONAL NUCLEAR ENERGY GENERATING COMPANY <ENERGOATOM>

NOK NORDOSTSCHWEIZERISCHE KRAFTWERKE

NPCIL NUCLEAR POWER CORPORATION OF INDIA LTD.

NPPD NEBRASKA PUBLIC POWER DISTRICT

NPQJVC NUCLEAR POWER PLANT QINSHAN JOINT VENTURE COMPANY LTD.

NUCLENOR NUCLENOR, S.A.

NUCMAN NUCLEAR MANAGEMENT CO.

OKG OKG AKTIEBOLAG

OPG ONTARIO POWER GENERATION OPPD OMAHA PUBLIC POWER DISTRICT PAEC PAKISTAN ATOMIC ENERGY COMMISSION PAKS RT. PAKS NUCLEAR POWER PLANT LTD PGE PACIFIC GAS & ELECTRIC CO.

PP&L PENNSYLVANIA POWER & LIGHT CO.

PROGRESS PROGRESS ENERGY CORPORATION PSEG PUBLIC SERVICE ELECTRIC & GAS CO.

QNPC QINSHAN NUCLEAR POWER COMPANY

RAB RINGHALS AB

REA ROSENERGOATOM, CONSORTIUM

RGE ROCHESTER GAS & ELECTRIC CORP.

RWE RWE ENERGIE AG

SCE SOUTHERN CALIFORNIA EDISON SCEG SOUTH CAROLINA ELECTRIC & GAS CO.

SHIKOKU SHIKOKU ELECTRIC POWER CO.

SNN SOCIETATEA NATIONALA NUCLEARELECTRICA S.A.

SOUTH SOUTHERN NUCLEAR OPERATING CO.

32

TEPCO TOKYO ELECTRIC POWER CO.

TOHOKU TOHOKU ELECTRIC POWER CO.

TPC TAI POWER CO.

TQNPC THE THIRD QINSHAN JOINTED VENTURE COMPANY LTD.

TVA TENNESSEE VALLEY AUTHORITY TVO TEOLLISUUDEN VOIMA OY TXU TXU ELECTRIC CO.

UFG UNION FENOSA GENERATION S.A.

WOLF WOLF CREEK NUCLEAR OPERATION CORP.

CONTRACTORS

AA ALSTHOM ATLANTIQUE

ABBATOM ABBATOM (formerly ASEA-ATOM)

ACECOWEN ACECOWEN ( ACEC-COCKERILL-WESTINGHOUSE ) ACLF (ACECOWEN - CREUSOT LOIRE - FRAMATOME) AECL ATOMIC ENERGY OF CANADA LTD.

AECL/DAE ATOMIC ENERGY OF CANADA Ltda AND DEPARTMENT OF ATOMIC ENERGY(INDIA)

AECL/DHI ATOMIC ENERGY OF CANADA LTD./DOOSAN HEAVY INDUSTRY &

CONSTRUCTION

AEE ATOMENERGOEXPORT APC ATOMIC POWER CONSTRUCTION LTD.

ASEASTAL ASEA-ATOM / STAL-LAVAL B&W BABCOCK & WILCOX CO.

BBC BROWN BOVERI ET CIE

CE COMBUSTION ENGINEERING CO.

CGE CANADIAN GENERAL ELECTRIC

CNCLNEY CNIM-CONSTRUCTIONS NAVALES ET INDUSTRIELLES DE MEDITERRANEE CL - CREUSOT LOIRE , NEY - NEYRPIC CNNC CHINA NATIONAL NUCLEAR CORPORATION

DHICKAEC DOOSAN HEAVY INDUSTRIES & CONSTRUCTION CO.LTD./KOREA ATOMICENERGY RESEARCH INSTITUTE/COMBUSTIONENGINEERING DHICKOPC DOOSAN HEAVY INDUSTRIES & CONSTRUCTION CO.LTD./KOREA

POWER ENGINEERING COMPANY/COMBUSTIONENGINEERING EE/B&W/T THE ENGLISH ELECTRIC CO. LTD / BABCOCK & WILCOX CO. /

TAYLOR WOODROW CONSTRUCTION LTD.

FRAM FRAMATOME

FRAMACEC FRAMACECO ( FRAMATOME-ACEC-COCKERILL ) GE GENERAL ELECTRIC COMPANY (US)

GEC GENERAL ELECTRIC COMPANY (UK)

GETSCO GENERAL ELECTRIC TECHNICAL SERVICES CO.

HITA/GE HITACHI LTD./GENERAL ELECTRIC CO.

HITACHI HITACHI LTD.

KWU SIEMENS KRAFTWERK UNION AG KWU/STOR KRAFTWERK UNION AG / STORK M MITSUBISHI HEAVY INDUSTRY LTD

MAEP MINATOMENERGOPROM, MINISTRY OF NUCLEAR POWER AND INDUSTRY

MNE MINISTRY OF NUCLEAR ENERGY OF RUSSIAN FEDERATION

NEI.P NEI PARSONS

NNC NATIONAL NUCLEAR CORPORATION NPC NUCLEAR POWER CO. LTD.

NPCIL NUCLEAR POWER CORPORATION OF INDIA LTD.

OH/AECL ONTARIO HYDRO / ATOMIC ENERGY OF CANADA LTD.

PAA PRODUCTION AMALGAMATION 'ATOMMASH', VOLGODONSK PAIP PRODUCTION AMALGAMATION IZHORSKY PLANT

ATOMMASH,VOLGODONSK,RUSSIA PPC PWR POWER PROJECTS

SIEM,KWU SIEMENS AG, KRAFTWERK UNION AG

SIEMENS SIEMENS AG

SKODA SKODA CONCERN NUCLEAR POWER PLANT WORKS TNPG THE NUCLEAR POWER GROUP LTD.

TOSHI/GE TOSHIBA CORPORATION/GENERAL ELECTRIC CO.

TOSHIBA TOSHIBA CORPORATION

UKAEA UNITED KINGDOM ATOMIC ENERGY AUTHORITY WEST WESTINGHOUSE ELECTRIC CORPORATION

6. DATA SHEETS ON

INDIVIDUAL NUCLEAR POWER STATIONS UNITS

1. 2.

Unit Capability Factor (in %)

Cumul.

Energy GW(e).h

Performance for Full Years of Commercial Operation

5600 63.9

1983

Energy Availability

Factor (in %) Load Factor (in %) Annual Time Online Capacity

MW(e)

Annual Cumul. Annual

77.8 59.8 77.7

1982 335.0 59.2 77.8 59.2

Annual Cumul. Hours of (%) 2666 hours

67.2%

Cumulative Load Factor:

Cumulative Unit Capability Factor:

Year

1753.6

31.2%

Total Off–line Time:

58066.2 GW(e).h 70.2%

19 Mar 1974

29.8%

Cumulative Energy Unavailability Factor:

Lifetime Generation:

Cumulative Energy Availability Factor:

77.1%

Historical Summary

Date of Commercial Operation:

Date of First Criticality:

Date of Grid Connection:

Date of Construction Start:

24 Jun 1974 01 Jun 1968 13 Jan 1974

2003 Monthly Performance Data

2003 Summary of Operation

7.2

UCLF replaces previously used UUF.

0.0 0.0 0.0 0.0

100.0 93.3 0.2 26.9

52.9 76.3 91.4 100.0 100.0 100.0 99.9 100.0 55.6 100.0 100.0 53.6 73.9 89.8 100.8 100.6 100.4 99.7 99.3

88.9 100.0 100.0 100.0

0.0 6.7 99.8 73.1

100.0 100.0 100.0 53.6 99.5

239.6 131.8 0.0 6.7 99.8 73.1 88.9 100.0 100.0

0.0 8.3 100.1

Nov Feb

0.0 16.0 239.8

0.0 6.4

250.7 242.0 248.7 Jan

0.0 184.2 216.6 251.3

0.0

May Jun Jul Aug Sep Oct Dec Annual

AR-1 ATUCHA-1

Operator:

Contractor: SIEMENS (SIEMENS AG)

NASA (NUCLEOELECTRICA ARGENTINA S.A.)

68.8%

68.9%

69.6%

Production Summary 2003

Energy Production: 2020.6 GW(e).h

Station Details

PHWR

Energy Availability Factor:

Design Discharge Burnup:

335.0 MW(e) 319.0 MW(e) 5600 MW.d/t

Load Factor:

Operating Factor:

Energy Unavailability Factor:

Type:

Maximum Net Capacity at the beginning of 2003:

Design Net Capacity:

EAF UCF

Mar Apr

0.0 0.0

2356.0 335.0 78.4 77.9 78.4 77.9 80.3 78.0 8101 92.5

1984 1706.1 335.0 98.7 80.0 98.7 80.0 58.0 75.9 8678 98.8

67.2 3030 34.6

68.9 67.2

72.3 68.8 70.2

6.

7.

A.

B.

C.

D.

E.

H.

J.

K.

8.

Date Hours GW(e).h Type Code 01 Jan 2112.0 707.5

2003 Outages

Description

PF D11 REPLACEMENT OF FUEL CHANNELS AND CONTROL RODS GUIDE TUBES, INSTALLATION

AR-1 ATUCHA-1

AND COMISSIONING OF A NEW EMERGENCY FEEDWATER SYSTEM AND TURBINE INSPECTION

AND COMISSIONING OF A NEW EMERGENCY FEEDWATER SYSTEM AND TURBINE INSPECTION

Documents relatifs