/u (.*'*.79
World Health Organisation
African Programme for Onchocerciasis Control
Assessment of the
sustainability of the
Masindi CDTI project
June 2002
Richard Gibson
Rose Korugyendo
James Mugisha
n
Index
Page Abbrevi ations/ acronyms and acknowled gements
Executive summary
Introduction and methodology Findings and recommendations
1. Distict level
2. Health centre level
3. Community level
4. Overall sustainability grading for the project Detailed findings
1. Health district
2. Sub-districil first line health facility level
3. Community level
4
Abbreviations/ acronyms
African Programme for Onchocerciasis Control Chief administrative officer (DCAO - Deputy CAO)
community directed distributor (of ivermectin) community directed treatment with ivermectin Deputy Director Health Services
District Onchocerciasis co-ordinator (ADOC - Assistant DOC)
District health team District management team
Local government level I (Incal council)
Local govemment level 3 (sub-county govemment) Local goverrrment level 5 @istrict government) non-governmental development organisation national onchocerciasis task force
Primary Health Care World Health Organisation APOC
CAO CDD CDTI DDHS DOC DHT DMT LGl
LG3 LG5 NGDO NOTF PHC
wHo
Acknowledgements
We would like to thank the following persons for their help:
' The staffat APOC Headquarters in Ouagadougou: Dr S6k6t6li, Dr Amazigo, Mr Aholou
. Dr. Richard Ndyomugyenyi, NOC, Kampala
. Staffof the District Health Services in Masindi: Dr. Luwaga (DDHS), Byaruhanga
Cosmas(DOC) and Mugayo William (ADOC)
' Health workers and community members attached to the Bulisa, Nyantonzi and Budongo
health
units.Executive summary
The Masindi
CDTI
project has been supported by APOC for the past 4 years, and is in its last year of agreed funding from APOC. An evaluation of the sustainability of the project was carried out in ApriV May 2002,by a team of evaluators. The evaluators were charged with three tasks:.
Evaluating the sustainability of the project..
Workingwith
local stakeholders to plan for sustainability, based on the f,rndings of the evaluation..
Advocacywith
local political andcivil
service leaders, regarding their future role in the sustainability of the project.The evaluation was carried out over a period of eleven days. Inforrnation was collected by document study, interview and observation, at sanpled sites at three levels of the health service: District, sub-district/ health cenfre, and village/ community.
The
overrll
judgement of the team isthat
theMasindi CDTI project
is notfar from
being sustainable.Regarding the six elements of sustainability, the situation is broadly as follows:
.
Efectiveness: The project is effective at all levels.
Eficiency/financing:
Many activities are not properly targeted, resulting in ineflicient use of scarce resources. I-ower levels (health center / supervisors and community) are not yetfully
empowered to carry out tasks at their level, even though the involvement ofstafffrom
higher levels is minimal..
Simplicity: Systems have been put in place for most processes, which may not be the most simple but function..
Integration: Due to the fact that funding has been parallel, most activities are still not integrated becauseit
has never been necessary or desirable to integrate thern
.
Atlitude: Although stakeholders have accepted the project as part of their routine work, some key players have not yet accepted the fact that theywill
have to cope without outside resources in the near future.There is evidence of political commitrnent to the project but very
little
actual involvement..
Resources:In
this key area the projectstill
relies too heavily on APOC. There is a willingness to fund the program atall
levels ofgovernment, but thus far the desire has not seen material expression, largely because it has not been necessary.Overall, it is apparent that because
CDTI
developed as a separate progranL with separate funding and separate requirements from role player, the need for involvement has beenminimal.
Consequently, the actualinvolvement of
r"any
players, as required for sustainability, has been minimalRegarding the position of the different levels of the project, at all levels there are problems requiring attention in the areas of leadership, training / mobilization and financing /
funding.
The communities are not significantly involved in plarming, while.at the district and health center levels supervision / monitoring remains a problern Detailed recomrendations were drawn up, based on the findings of the evaluation at the four levels. The recommendations were prioritised, and indicators and deadlines were suggested for each. The most important recommendations concern:.
Determining the exact fi.rnding thatwill
be available, and mobilising additional sources of frrndingif
necessary.
'
Tailoring activities (mainly training and supervision) to frt the budget.'
Enpowering the supervisors and communities to takefull
charge of activities at their levelsAdvocacy activr;:es were carried out at the level of the District (LG5 Chairman, Chlef Finance Officer, Deputy Chief Adminisrrative Officer, DDHS) and interim levels of government (Health Sub-distnct chref, LC3 chief, LC3 sub-accoun:ant).
One feedback / planning session was
held. It
was envisaged that the people rnvolved in annual planning for CDTI in this pro:ect, should attend to revisit the project plans for thefurure.
It was decided to include as rnany members ofoths
levels of government, not included in CDTI activities to date, as possible. People were rnvrted from Hea.lth sub-district and LC3 levels, levels of government not involved in CDTI activities to date, but necessaryfor
future sustainability.The uorkshop process was not particularly successful due to a combinatron
of
lack of experrence of facilitators and relicence on '-he part of particlpants. Although participants agreed wrth the findings of the evaluation tearq dunng the plann-rrg process they haddifficulty
changing mrndset and questioning activitres. This process was not helped by the fact that all members of the different levels of government kept grvrng assurances that they u'ould accept responsibility for allCDTI
activitres, within their area of influence, creatinS, the impression that6
the status quo would be maintained. Time for the process was limited, and so all of the goals of the meeting were not achieved
-
problem with experience.One positive outcome of the meeting was the cornmitment from all levels of government to support the CDTI process and determination to succeed. Government participans were made aware of the new requirements
of
CDTI and "guaranteed" the sustainability of the project.Introduction and methodology
1. Introduction
The Masindi CDTI project was one of the first group of projects to be approved by APOC, and to begin receiving funding in 1997 havng previously been engaged in other Mectizan distribution activities. Its 5 year period of funding is due to end in November 2002.
In 2001
adecision was taken by APOC management that all projects should be
assessed,to find out how sustainable they are. The Masindi project is one of 4 projects in Uganda which were evaluated for sustainability at this time
Accordingly the aim of this assessment was twofold:
. To
assessthe level of sustainability of the Masindi project.
. To feed back the findings of the team, and to undertake
aworkshop in which these findings are used in the planning process for next year.
The political arrangements in Uganda did not fall within the neat allocations of the instruments developed for this study.
Uganda is involved in
aprocess of decentralisation of authority, whereby planning and implementation of activities is carried out at the lowest possible level of govemment, while the higher levels are involved primarily in supervision and facilitation. This process is new, and it appqrs that the CDTI process
hasbypassed entire levels of government.
Govemment structure is
asfollows:
. National, district (LG5),
. health sub-district,
. sub-county (LG3),
. health centre and
. local (community) council (LGl).
The CDTI process has involved the following levels of health care
, National, . district,
' health centre and
. local (community) council
2. Methodology
This is given in detail in the document: 'Using the instrument to determine the sustainability of APOC projects'.
Research question: How sustainable is the Masindi CDTI project?
Des ign :
Cross-sectional, descriptive.
Population: The Masindi project, including: the DOC and district Ievel staff, the zonal supervisors, the health centres, the CDDs
andthe communities in Onchocerciasis endemic areas.
Sampling:
I
8
* In the district of Masindi, Onchocerciasis affects 2 sub-districts, therefore both sub- districts were sampled (Bulisa and Bujenje)
* Within the two sub-districts, only 3 health centres are affected, therefore all three health centres were sampled (Biiso, Nyantonzi and Budongo). Zone supervisors, who may or may not be health centre staff, function in the role of the "front line health
unit"
asdescribed in the instrument. As far
aspossible these people were included in the sample, in addition to the health centre staffengaged in CDTI activities.
* Within each health unit, two villages were sampled, one with low coverage, one with high coverage (Kihuuh4 Bubwe, Nyantonzi TC, Bisaju II, Kyempunu and Maramu), these villages also fulfilled the criteria for endemicity (high and low rates included) and accessibility (accessible and inaccessible villages included).
Instrument:
* Questionnaire (see appendix: 'Detailed findings') structured
as aseries of indicators of
sustainability. The indicators are grouped into 9 categories.
* The instrument
assessessustainability at levels of operation.
* The instrument guides the researcher to collcct relevant information about each indicator.
Source of information:Yerbal reports from persons interviewed, supplemented by documentary evidence.
Analysis:
* Based on the information collected, each indicator is graded on
ascale of 0-4, in terms of its contribution to sustainability.
* The avemge 'sustainability score' for
eachgroup of indicators is calculated, for each level.
* A qualitative description of problem
areasis given.
Limitations of the study were found to be the following:
* The people, at all levels, required for interviews were generally not prepared for the visit, which coincided with trips out of the country / district, market days, workshops, etc. Much time was spent mobilising suitable people.
* The dosumentation required was not ready and often not available - the respondents were not informed of this need in advance and it appears that record keeping at all levels, above that of the CDD, is not
apriority issue.
I
9
Masindi Project: Self-sustainability at district level
4 3.5
sr ;
.c. uE 6 -'-
6 ,2
o
B
r.si1
o 0.50
./ '*{'""""Py
Group of indicators
Findings and recommendations
1. District level
1.1 Overall grading (on a scale of 0-4)
1.2 Main findings
Coverage:
Overall and geographic coverage are excellent Plannine:
Detailed year plans are apparently developed for CDTI, which are separate to the plans for the rest of the DMT and do not involve members of the DMT who are not directly
engaged
in CDTI activites.
Leadership:
The CDTI program is initiated largely by an annual planning workshop, hosted by the NGDO, in cornbination with Hoima district. Civil service decision makers (DDHS and DCAO) have been effectively included into the program.
Monitorine / Supervision:
District staff meet supervisors annually and at quarterly meeting (5 tinres per year)
ass'ell
asduring routine reporting meetings. Also involved in supervision of activities of
supervisors in form of spot checks. Planned visits to villages during'activities no evidence of
reasonsfor specific visits - involve only CDTI staff and few civil servants, not rest of
D\{T.
Repor':'-ingis via
aparallel system, with monthly reporting and activity reporting.
Although problems are addressed at this level, there is little evidence of empowerment of
people
at lower levels.
t
n."".o.
l0
Mectizan:
The ordering and distribution of Mectizan is via
aparallel system, yet appears to be sustainable and effrcient.
Trainine / Sensitisation / Mobilisation:
Training of supervisors and CDDs takes place annually, regardless of requirements.
District staffare mostly involved in supervisor training but also engage in CDD training -
spot checks and support. Stake holders meetings
areheld annually, involving people at all levels of government, but there is no evidence of
thesepeople becoming actively engaged in supporting CDTI.
Financine / Fundine:
Budgeting in the district is based on
abottom-up approach but availability of APOC funds
hasremoved requirement of "lower" levels of government to become involved in financing. All CDTI activities are included under "PHC ou.treach", with no evidence of
careful planning for requirements of any individual element and separate CDTI planning according to APOC requirements.
Material Resources:
The
useof transport is integrated at this level although vehicles are usually used for separate activities - due to the allocation of staff responsibilities. Control of vehicle use
atthis level is poor.
Human Resources:
Human resources at this level are knowledgeable and skilled, this is helped by regular salaries. There is no integration of activities between members of the DMT.
1.3 Recommendations
Recommendation Implementation
Plannine:
. District staffshould include other DHT members into their planning activities
. They should consult with sub-district and sub- county staffduring the planning process
Priority: HIGH Indicators of
success:. Evidence of other DHT staff
including CDTI in their routine activities
. Inclusion of CDTI in the planning and budgets at these levels
Wo to take action
. DDHS / DHT
. DOC
D eadl ine
for
comp I e t i o n. June 2002 The political and administrative leaders
atthe
sub-district and sub-county levels should be included in the CDTI process
These leaders should be encouraged, thereby, to carry resf,onsibility for CDTI activities in their
areas.
Priority: HIGH
I nd i
cators of
suc ces s'.. Targeted meetings with leaders
having,speci
fic
objectives
. Reflected
asabove
Ll/ho
to take action
. DDHS / DHT
. DOC
Leadership.
Deadline for completton:
June 2002 Supervision and Monitorins.
. District staffshould try to further empower
supervisors to identify and manage problems with CDTI by systematically discussing reports and encouraging management activities
Priority: MEDIUM Indicators ofsuccess;
. Supervisors ability to identify and manage problems reflected in
reports
Who to take action:
. DOC/ADOC
Deadline for completion:
. December 2002
Trainine.
. Training programs should focus
lesson structured meetings and more on on-site kaining during normal activities of the DHT
Priority: Medium Indicators of success:
. Fewer training workshops
arranged in year
. Training activities carried out during routine health activities.
Deadline for completion : December 2002.
Fundine.
. CDTI activities need to be revised within the available district budget.
. With increasing involvement of sub-district and sub-counf5r structures
asabove, they need to be strongly encouraged to contribute financially to CDTI activities
Priority: HIGH Indicators of success:
l. Consideration and reflection of
costs of all CDTI activities in
detailed plan
2. Reflection of CDTI activities in S/D and S/C budgets
1. DOC / ADOC
2. DHT
Deadline for completion:
December 2002 Who to take action:
' DOC
. DHT
,,
t2
Sub-district Level (Health Unit)
Overall grading (on a scale of 04)
2.1
Masindi project: self-sustainability at health centre level
"""". ,"."""
.."t""
""t"
4 3.5 ttJ E 2.5
EDo^
o
,z
tD t<
lg"-
o
>1
0.5 0
,u,"- -"""
Group of indicators
2.2 Main findings
Coveraqe:
Overall and geographic coverage
areexcellent Plannine:
CDTI is seen
asbeing core activity of the health centres and detailed planning takes place
atthis level. However only staffidentified
assupervisors are included in the planning and activities.
Leadership:
CDTI activities are initiated by
andrespond to the demands of the district staff.
Supervisors are expected to perform activities dictated by district and report to district, they then receive allowances from district. There
appearsto be political commitment to CDTI at this level, although active involvement
hasto
datebeen limited.
Monitorinq / Strpervision:
There is excessive supervision
andmonitoring by supervisors. It is standard practice for supervisors to observe CDDs in action. All activities are carried out
asroutine -
regardless
of need - with little evidence of response to problems. Supervisors identify problems with CDTi activities in their
areas,but no evidence of activities to deal with
these.Reporting on CDTI activities follows
aparallel procedure, excluding rtormal levels of
government.
I
-..c
*.@"
Mectizan:
The distribution of Mectizan is proceeding efficiently despite the fact that it follows
aunique path. Mectizan is
seen asbeing an essential drug at this level. Ordering is directly to the DOC on the basis of census figures. Disitribution to health centres is by project staff.
Cotrol of Mectizan is separate, making use of CDDs reports, not stock control cards.
Trainine / Sensitisation / Mobilisation:
Training of CDDs is
aroutine procedure lasting for 3 days regardless of needs of
CDDs. Sensitisation at this level is minimal, LC3 reports minimal sensitisation. Most sensitisation targeted to LCI - and this mostly routine. Materials are mostly unavailable -
many CDDs are not health centre staffwith no materials - and where available
aredifficult to
renew.
Financine / Fundine:
Health centre activities
areincluded under PHC outreach. Despite detailed CDTI plans for APOC, no evidence that these plans used in determination of health centre budget.
Supervisors activities and allowances separately funded and have not been included in government budgets to date.
Material Resources:
ln some
areasthere are too many supervisors, not enough bicycles. Use of health centre transport is integrated although trips tend to be for specific activities.
Human Resources:
Supervisors
arewell trained and motivated. The system of supervisors developed
becausehealth centre staff were unable to cope with demands of CDTI activities. It is of
concern that should the system of supervisors fail, it is unlikely that the health centres will
cope with the current burden of activities.
2.3 Recommendations Plannine.
. Health centre staff should plan for reduced, targeted CDTI activities
Priority: MEDIUM Indicators of success:
. Targeted activities reflected in work plans Who to take action:
. Health centre staff
D
eadline for completion
. December 2002 Leadership:
. Health centre staff should continue to
raiseissues around CDTI with LC3 politicians
' LC3 budgeting authorities should be encouraged to embrace the system of
supervisors from outside the health
system.Priority: MEDruM Indicators ofsuccess:
. Increased awareness of LC3 pesonnel about CDTI
. Budgetary allowances for supervisors
Wo to take action:
1. Health centre staff 2. DHT
D
eadline for comp'letion
' December 2002
Supen'ision Priority: MEDruM
t4 Supenrision needs to move from routine to superuision focused on identifying and managing problem
areas.Supervisors should hold focus goup
discussions with LCl, CDDs and
communities to empower
thesepeople to identiff and manage problems.
Indicators of
success:. Fewer supervisory contacts, justification for all contacts
' Detail of discussions to be included in activity reports
Who
to take action:
. Supervisors
Deadline for completion:
. December 2002 Training:
. Training needs to become
lessroutine and more focused with fewer, shorter training
sessionsand more on-site training.
. Training should occur at the
sametime
asother health activities
Priority: MEDIUM Indicators ofsuccess:
. Cessation of routine training meetings
. Justification for training sessions
r Integration of health related visits.
Who
to take action:
. Supervisors
Deadline for completion:
December 2002 Fundine.
. LC3 politicians must be strongly
encouraged to include CDTI activities in their budgets
Priority: HIGH Indicators ofsuccess:
. Inclusion of CDTI activities in annual budget
Wo to take action:
. Health centre staff
. DHT
Deadline for completion:
Jlune2002 Human resources.
. The
useof supervisors should be reviewed
andnumber and activities should be determined by available resources.
Priority: HIGH Indicators ofsuccess:
. Detailed plan of supervisor activities against available resources
Who
to take action:
. Project staff(DOC, NGDO, Supervisors) Deadline for completion:
December 2002
I
a
3. Village level
3.1 Overall grading (on a scale of
G-4)4.2 Main lindings
Coverage:
Overall and geographic coverage are excellent Plannine:
There is no evidence of planning at this level, CDTI personnel respond to requirement of higher levels. Census update and distribution separate.
Leadership:
The local council
as awhole is minipally involved in CDTI.
Monitorins / Supervision:
Repor-ting is accurate and complete. Supervision of activities at this level remains the
responsibility
of supervi sors.
Mectizan:
There have been no delays with distribution and sufficient Mectizan has been
received. Orcering based on census figures, when census has to be cancelled due to delayed
finances,ordcring has been based on previous year's figures with no problems in distribution.
Trainine / Sensitisation / Mobilisation:
LOC members are poorly aware of CDTI activities. CDDs claim to be involved in sensitisation but no evidence, it appears that sensitisation remains
aroutine activity carried out b)'superv'lsors.
Masindi project: self-sustainability at community level
4.5 4
+
3.5E3
vtD6
2.53
o2
TD
8..
o r.J
0.5 0
^9'
"t.''
*.""
a\o'
*.--;"""'.".""",
Group of indicators
l6 Financine / Fundine:
CDTI is seen
asan externally funded, government run program. Half of communities provide incentives to CDDs from tax receipts.
Material Resources:
Transport is not
aproblem at this level.
Human Resources:
CDDs are trained and knowledgeable. It is
seen asbeing impossible for CDD training to take place at this level, it requires input from higher levels. CDDs and communities
appreciate the benefits of Mectzan and appreciate the need for long term treatment.
4.3 Recommendations Plaunins:
. The work of the CDD can be simplified by combining activities (e.g. census and distribution)
Priority: MEDIUM Indicators of success:
. Streamlined plan of activities
Wo to take action:
. Supervisors
. CDDs
Deadline for completion
' December 2002
Leadershio.
. [ocal councils should be encouraged to
acceptresponsibility for
management of locally relevant problems including follow-up of non- compliant community members.
Priority: MEDIUM Indicators ofsuccess:
' CDTI becomes regular feature in local council discussions
Who
to take action
. Supervisors
. CDDs
Deadline for completion
December 2002 Fundine.
. [ocal councils should be encouraged to support CDDs from the
25Yoof G- Tax,
asmedical expenditure
Priority: MEDIUM Indicators of success:
. Local councils offer incentives to CDDs.
lVhq to take action:
. LC3
. Supervisors
Deadltne for completion
:December 2002
4. Overall sustainability grading for the Masindi project
The overall irryression is ttrat the potential for sustainability is
high.
Although various problems have been identified with the prograrq most of these problems have arisen as a result of the systemof
funding the
prograrn
APOC money has been available, with its attendant requirements, makingit
diffrcult for systematic inclusion of the CDTI process into the mainstream of planning, budgeting and rnanagement. There is strong commitrnent to the program at all levels of political decision making, people see this as a Masindi prograrrt which the people of Masindiwill
manage. Additionally there is evidence that Mectizan was distributed before the advent of APOC, and there is a belief that there is no reason why distribution should not continue after APOC, as long as the supply of the Mectizan is assured.There is a lot
of
pride in the achievements of CDTI, and enthusiasm that all role players arefinally
being brought on board.
Tick one correct assessment
Level
of
sustqinabiliv
Description
Excellent This proiect is completely sustainable
This project is not far from being sustainable. With feedback from the team before departure, the project staffshould be able to undertake the required remedial action.
Moderate This project is potentially sustainable, but
will
require rethinking and mobilization of high level support to get it on the road again.Low
This project is seriously unsustainable-
there is some doubt as to whetherit
ever
will
be. It needs a lot of immediate expert zuidance from outside.-
l8
FEEDBACK /PLANNING
WORKSHOP,MASINDI
4 JUNE 2OO2
Attendance list.
NAME
POSITIONDr. Henry Luwaga DDHS
Byaruhanga Cosmas DOC
Mugayo
William
ADOCKasangaki Francis Sub-county chief, Budongo
Kiningi
John In Charge, Bulisa Health sub-district Bigabwa James In Qarge, Biiso health centreKyomye Rumbeiho Chairmaq Pakanyi
Byaruhanga Jack SACAO / Bulisa
Dr. G.Idayiko In Charge Bujenji Health Sub-district Mugenyi Malitubu Chairpersoq Biiso
Bategeka Joronim
Ql*!rr"u,
LC3, BudongoAntama Fred E / N, Budongo Health Centre Kirokimu John H / A, Biiso Health Centre
Mboineki
KCM
HMIS FP, DDHS officeKazimura Alice N / A, Biiso Health Cenhe
Bukya Wilson S / Aide, Kinyara
Kyamanyira Dominic Rec Assistant, Nyantonzi Health Centre
Oyewa Denis Superviqor, Biiso
Kaahwa Bagonza Supervisor, Biiso
Kaija Ateenyi Ellison Supsryisor, Biiso
Asiimwe Jeska Supervisor, Biiso
Opomo Jane Supervisor, Nyatonzi
Byakagaba
Elly
Supervisor, KaseneneDramadri
Alfred
Supewisor, KaseneneNibihi Aniiku
Supervisor, Kibwona Katumba Charles Supervisor, KinyangNsubuga Yosam Supervisor, Nyantonzi
Asiya John Supelyisor, Nyantonzi
Isuigoma David Supervisor, Hyabyeya
Avutia Emmanuel Supervisor, Nyantonzi
Problems identified.
Those in bold were identified by the evaluation team, and adopted by the participants.
Those
in italtcs were added by
theparticipants Finance.
Parallel funding Separate planning No pressure to fund
Inaccessible / latefundingfrom sub-county / health sub-district Monitoring / Supervision
Too much routine supervision Not empowering
No action results from activities Lack of health stalffor these activities Planning.
Not bottom up lntegration
Plans are not implemented as scheduled Training.
Few are trained
Training takes long hence expensive Untargeted training
Mobilisation.
Low turn up
Lack of collaboration among some local leaders Some religious sects reject
theprogram
Leadership.
At all
levelsfew are involved
Inadequate political support at all levels Material Resources.
Lack of bicycles to supervisors and CDDs Lack of fuel for motorcycles at health unit level Lack of bicycle maintenance allowance
Lack of protective gear (gum boots and rain
suits)for supervisors during
ratny season.
20
Possible solutions.
Material Resources.
Increase the number of CDDs so
asto
decreasethe number of households per CDD
lntegration of activities.
Leadership.
Advocacy for the program for all stakeholders lntegration of CDTI activities into health activities Have a focal person at Health Sub-district
Mobilisation / sensitisation of LC
1- 5 on CDTI progrzrm
Planning.
Planning should be bottom up. tn the
debatewhich followed this statement, it
was decided that bottom up means consulting at all levels with leaders.
It should be integrated at all levels.
Stake holders to consider this program
aspriority
Training.
Implementors should be committed.
Implementors should adopt the idea of volunteerism Local leaders should also be trained to boost the CDDs Training should last for only one day
Training should be targeted, excluding those who are experienced.
Mobilisation.
All stake holders should get involved in mobilisation.
Leaders must be seriously sensitised More sensitisation to those religious
sects.Finance.
Joint planning at all levels encouraging provision of Onchocerciasis activities Political will
Monitoring / Supervision.
Integration of supervision activities Focus goup discussions at all levels
Follow up of resolutions after workshops
Empower LCs and CDDs to restrict supervision to
aminimum
AgTIVTTY
WHY DO WE NEED TO DO THIS?WHO SHOULD DO THIS?
WHEN MUST
IT
BE DONE?WHAT
RESULTS DO WE EXPECT?Pakanyi Remaining part of 2002 Mobilisation
of
local communities and teachers
To create awareness to our communities
/
leaders
of
Onchocerciasis as a disease
Supervisors June 2002 Number of meetings
held
Training of CDDs Refresh CDDs on their roles
Supervisor June 2002 No of CDDs trained
Distribution
of
ivermectin
To eradicate oncho CDD July 2002 increased number
of
people taking Ivermectin Supervision Ensure effective
distribution
Supervisors
luly
2OO2 Increased numberof
beneficiaries Data collection Assess level
of
performance / record keeping
Supervisor Aug
-
Sep 2002 High coverageFeedback Give feedback to the beneficiaries
Supervisor
Dec2002
Magrritudeof
attendance Plan for 2003
Update ofcensus registers
To plan for the next distribution of tablets
CDDs / supervisors Jan 2003 Number
of
registered beneficiaries Sensitisation
/
mobilisation of local communities
To create awareness to communities about the disease
Supervisor Feb 2003 Number of meetings
held Training of CDDs Refresh the CDDs on
their role
Supervisors Mar 2003 No of CDDs trained
22
ACTIVITY WHY
DO WE NEED TO DO THIS?WHO SHOULD DO THIS?
WHEN MUST
IT
BE DONE?WHATRESULTS DO WE EXPECT?
Budongo Sub-county CDTI plan Updating
of
registers
As to budget Community leaders, supervisors, CDDs
Dec2002
Update census figures Community andlocal leaders sensitisation
Create awareness
of
Onchocerciasis activities
CDD, community leaders, supervisors
Jan 2003 Number of local leaders participating Select and
rain
more CDDs
To reduce on the area of distribution
Community and supervisors
Feb - March 2003 Number of selected and trained CDDs Supervision and
monitoring
of
ivermectin distribution and data collection
To check on corrpliance
Supervisors, local leaders
June 2003 Number of people treated
RESOI.IRCES WHERE CAN WE
OBTAIN THIS RESOURCE?
HOW CAN WE
OBTAIN
THISRESOURCE?
HOW SURE ARE WE TTIAT WE
WILL
GET THIS RESOURCE?Human Community
Health services
Mobilisation / selection DDHS
Sub-county budget DDHS budget
Materials Sub-county
Health services
Sub-county budget DDHS budget
Incorporated in the sub- county and DDHS budgets
Financial
District
NGO Sub-county Community
Presentation of proposals Sub-county budget 25% contribution from
LCI
Fuel for distribution and support supervision incorporated in DDHS budget
Biiso Sub-county CDTI work plan
ACTIVITY WHY
DO WENEED TO DO THIS?
WHO SHOULD DO THIS?
WHEN MUST
IT
BE DONE?WHAT
RESULTS DO WE EXPECT?Updating register To know the population to serve
LCI,
CDDS, supervisorsNov
-Dec
2002 To seeif
the new people are there The increase and decreaseof
population Mobilisation and
sensitisation
of
community leaders and teachers
Create awareness Supervisors Jan 2003 To get more
involved and get necessary support Training of CDDs
newly identified
So that get the concept
ofCDTI
proiectSupervisors Feb 2003 Functional CDDs
Support supervision of ivermectin distribution
To make sure that the community has swallowed the tablet
Supervisors Feb 2003 At95Yo coverage
should swallow the tablet
Data collection and reporting
To get the coverage and information
CDDs and supervisors
April2003
What has been done Feedback forum To makecommunity know
of
how tablet was swallowed
Supervisors June 2003 To get solution to
challenges
RESOURCES WHERE CAN WE
OBTAIN
THIS RESOURCE?HOW CAN WE OBTATN THIS
RESOURCE?
HOW SURE ARE WE
THAT
WEWILL
GET THIS RESOURCE?Stationary Sub-county headquarters
LGDP
HSD and PHC tunds
Forwarding requisition and budget
Assurance from the sub- county
Allowances Sub-county, Health
Unit
and PHC funds and other sources
Forwarding requisition and budget
Assurance from Sub- county
24
Detailed findings
Instrument2: health districU LGA level
Important
notes' By'district
rnanagement team'(DMT)
is meant: the persons heading up sections or departrnents in the districULGA
health service, and who function as a team in running that service. Someone in this teamwill
be responsible for communicable disease control programmes in the district/ LGA. The person actually running the
CDTI
progratnme in the district/ LGA is not necessarily a member of the DMT.'
Some of the topics in the instrument below refer to the functioning of theDMT,
and others to the functioning of the onchocerciasis control prograrnme at this level.I
To gather the information you you have to make use of the
following
sources:Interviews
with:
*
One or more knowledgeable members of the DMT, or district/LGA
healthteanl
including:-
The most senior person (e.g. the chairpersor; or district medical officer).-
The person responsible for CDTI at this level.-
The pharmacist for the health district/ LGA.-
The transport offrcer for the health district/ LGA.-
The finance/ budget officer of the districU LGA.*
The senior NGDO manager in the project, for that district/ LGA.+
The senior politician in the district/ LGA, who is charged with supervising health matters.These persons may need to be interviewed separately, since some may find it hard to disagree with others in their presence.
Documents:
*
The coveftlge reports/ tables for the health district / LGA for the past three years (per sub-district; per village)*
REMO reports, including lists of all endemic communities/ target populations*
The year plans for the healthdistict
/ LGA for the past two years:-
Inctuding the plans for CDTI (integrated with the main plan, or separate)- Also
quarterly or monthly plans(if
these exist)+
Theyeuly
budget for the last three years for the health district/LGA
(from all sources: theLGA
itself, higher levels of the government, APOC, the NGDO partrrer)*
Financial control documents: expenditure authorisation slips, joumals, ledgers etc.*
Reportsof
the last round ofCDTI
in the health district/LGA
*
Reports(if
these exist) of routine supervision visits byDMT
members, to the sub-districts* All
the forms related to ordering, issuing and control of Mectizan at the health district/LGA
level* All
curricula, training materials, timetables, attendance lists and reports relating to training for CDTI and in-service training in the health district/ LGA over the last two years* All repcts
of mobilisation/ sensitisation activities in the health district/LGA
in the past two years.+ All
dotrmrentation related to control and use of oflicial transport at thislevel, over the last two years: trip authorisations, fuel allocations, log books etc.NOTE:
'
Whenever documentary information is requested, rt is not enough to receive verbal assurances that the documents ezist. They have to be inspected physically.'
As far as possible information gathered from these sources should be corroborated by information gathered from sources interviews and documents at other levels.l.l
Check whether the geographical coverage in the health district/ LGA is satisfactory (indicatorof
I
.2
Checkif all
sub-districts and villages have a satisfactory therapeutic coverage rale (indicatorof
Findinss:
No REMO lists are available but all reports quote 100%
geographical coverage.
All
sub-districts and villages identified by the latest REMO should be under treatment (i.e. thegeographical coverage rate is I 00o% and stable).
This should be confirmed by comparing coverage records with the REMO list of endemic villages
Slightly (many villages/ hamlets
not covered) Is this criterion for sustainability
being
tulfilled?
Highly
(problemwith
nomads
Moderately (a few villages/ hamlets not
covered)
Findines:
Coverage is 14.4"h The therapeutic coverage rate should be:
.
65ok or higher'
stable or increasing.Slightly (less than 65olo coverage) Is this criterion
for
sustainabilitybeing
tulfilled?
Fully (>85%
coverage)
Moderately (65- 74%o coverage)
2.1 Check
rf
the year planfor
CDTI appears as part of an overall written planfor
the activities of the healthdistrict/
LGA(it
may appear under another name, e.g. 'onchocerciasis programme') (indicatorof
and
2.2 ftecktf
the containsall
the elements needed CDTI toworkwell
2.3
Checkif
theyearly plans were drawn up in a participatory way (the overall district/ LGAplarl
and theCDTI of effectiveness
3. Providing
leadership. -.
.,,,il-.:.,r*iti:-#'#ffiffi[
3.1
Checkif
thedistrict/
LGA health management team istakingfull
responsibilityfor
CDTI (the compositionof
CDTI should be integrated into the overall plan (showing that the DMT members consider CDTI to be part of their
yearly
routine, like any other programme) It should not be separate.Findines:
CDTI activities are planned in a different plan which is included in the year plan of the district
Fully
HighlySlightly
Not at all Not applicable Is this criterionfor
sustainabilitybeing
tulfilled?
The plan should make
provisionfor all
key elements.Checklist
of
ksy activities: Mectizan supply;urgeted training
;
targeted mobilisation/sensitisation ; monitoring and superttision t
I
Findines:
The plan was not seen but apparently makes provision for all activities
Fully
ModeratelySlightly
Not atall
Not applicable Is thissrilsri.n for
sustainabilitybeing
firlfilled?
ln both case*planning should involve
all
relevantstaff
(e.g. sub-district, pharmaceutical stafr) preferably in a vvorl<shop situation.
Findinss:
Plan nrade in session
witlr
supervisors, DMO, DOC, DDOC. NOC ancl Sight Savers. No evidenceof
1tar1 ic ipal ion ol' othcl nrc nrbers o l'
Dl\'ll'
Is this criterion
for
sustainability being tulfilled?Fully Highly Slightly Not at all Not applicable
Findinss:
I)r'olnrr)l irrrtiatcd
u'iilr
aidol'NOC
andN(ilX).
l)roccss stiltls i.lt hcrirrrrinuol'vcar.
lirllou,s sct patte rn.It should
te
the DMT which is initiating the key CDTI actit, ities: planning, monitoring/ supen,ision, training, Meclizan ordering/ distribution.The DMT r hould no longer depend on lhe State/
regional/
iiCDO
leadershtl to carry out CDTLa
I
Fully Highly Slightly Not at all Not applicable Is this criterion
for
sustainabilitybeing tulfilled?
of this team from to indicator of i and attitude
I
Moderatelj
26
3.2
Checkif
there is evidence ofpolitical
commitment to CDTI in the district/LGI
(indicatorof
integration and attitudeThe senior person (politician/ civil servant) in charge of health matters at district/ LGA level should
loow
about CDTI and appears committed to it.There should be evidence ofspecific past budgetary allocations and disbursements
for
CDTI, and theS and DCAO effectively included in
CDTI
activities.amounts should be
is a budgetary allowance for CDTI, unable to
if
increasing.Is this criterion for sustainability being tulfilled?
Fully
Moderately Slightly Not at all Not applicableThere should be evidence that each sub-district is visited at least once around the time of distribution.
There should not be unnecessarily many visits - here should be clear justification
for
each one.Only the sub-district should be routinely visited, not the villages.
rsits may be in response to needs or routine
health unit's visited routinely or for spot checks, all sors meet at the annual gathering and at quarterly
isits to villages for supervision of distribution and and community sensitisation involve DDHS
ADOC, NGDO Is this criterion
for
sustainability beingtulfilled?
Fully Highly Slightly Not at all Not applicable
4.1
Checkif
the relevant person at the LGA/ district level is routinely andeficiently
supervising the CDTIthe sub-districts on site ofeffectiveness and
4.2
Checkif
routine data concerning CDTI activities at this level are collected and transmitted entirely withinthe
of
Check u/hether there is a routine process of management of problems and successes, which are indicated by the monitoring system (coverage data, visits and reports) (indicator of effectiveness and attitude
4.3
The reporting process should be within the government
ng is via a parallel sytem because requirenrents are activ not rout
not using other resources
in the Is this criterion
for
sustainability beingtulfilled?
Slightly Fully Highly
I
Not at all Not applicable
oppropriate manager should deal with them- Planning must include activities which
will
improve coverage in areas whereit
is unsatisfoctory.Successes should be noted and reported, and appropri a t e fe e db ack giv en
The CDTI co-ordinator should be empowering the next level to cope with problems.
Checklist of key activities : sensitisation/ mobtlisation ; training; improving Mectizan supply ; effective/
es.Have additional visits to areas with problems As soon as problems are in this way, the
with most problems
evidence of positive feedback.
evidence of emporverment at lower levels
Is this criterion
for
sustainability being tulfilled?Fully Highly Not at all Not applicable
The order fc,-ms
for
the health district/ LGA exist,should be based on the sub-district orders.
The Mectizan should be available
for
the LGAs in timefor
distribution at o time which is convenient to villagers.There shoulc be no reports ofshortages.
there have been there should be
in lolrn
ol'lttttr
toN()('
hascrl on ccnsus llstrr e srrts ol'tlt'lavs or .rltorlage s.
\o
rc;'rr5.1
Checkif
'ient Mectizan is ordered and in Iime indicator of effectiveness fidud€raGlyM_o$!1ateJ51
ISlightly
5.2
Check if Mectizan is being stored and administered within the government system at this level (indicatorof
5.3
Checkif
Mectizan is being distributed appropriately and efectively to the sub-districts (indicatorof
plans to remedy them.
Is this criterion for sustainability being tulfilled?
Moderately Slightly Not at all Not applicable
The Mectban:
.
Should be orderedfrom the nu.t level usingforms supplied by the government..
Should be stored in a room made available by the governmerrt at this level - preferably in the same room as the other drugs..
Should be controlled within the government system, preferably using the same stock control system as for other drugs.Findinss:
Orders in fbrm of lette r to NOC based on census figures.
Delivered to DOC or pharmacy by project stafl, therefore may nol be stored in pharmacy.
Distributed by district stalf, no evidence of routine stock control being used.
Is this criterion for sustainability being tulfilled?
Fully
Moderately Slightly Not at all Not applicableThe sub-districts should obtain the Mectizan by means of transport supplied and
paidfor
by the government at the district/ LGA levelPreferably the sub-district shouldfetch the Mectizan from the district/ LGA level store.
Findines:
Distributed by district staff using vehicles in the district pool, maintained largely by district.
Slighay Not at all Not applicable Is this criterion for sustainability
being tulfilled?
Fully
Moderatelyili,il t1
6.1
Checkif
,s doneof
and6.2
Check thattaining
is being done at the appropniate level, by the appropriatestaf
(indicator of effrciency and6.3
Checkif
in- service u'ainingfor
CDTI is being integrated with other health programme training at this level Findinss:Training is performed annually at training sessions for which allowances received.
Directiy involved in annual training of supervisors.
Supervisors other areas of training.
There should be an objective needfor each episode of training:
*
There must be evidence thatstaf
to be trained lack laowledge and skills to perform thejob.
a
Trainbtg to motivatestaffis
not asuficient
reason
for
training.The evaluator must be satisfied that the duration
of
train ing was i ustilied.
I
Fully Highly
Moderately Not at all Not applicable Is rh;s criterionfor
sustainabilitybeing tulfilled?
Staffof thk level should only
tain
the level immediately below it, and nrtlfurther
down.Findines:
Irocus ol'trainirtg is rlrt strpcrr isors hut irrr olvc<l in
CD[)
trairrinu as u'cll.Is this criterion for sustainability being tulhlled?
Fully
Moderately Slightly Not at all Not applicableFindines:
'l rarnirrg lakcs tltc tirrttt ol'solksltrrps altd tlucs lrot fi)rnr parl ol'tlre routinc tra\rring activrtie s irr thc tlistrrct.
Trainingfor CDTI should be integroted into the yearly
planfor
in-ser,'ice training in the health district/ LGA.Fully
Highly Moderatelym
Not at all Not applicable Is this criterion for sustainabilitybeing tulfilledt,
indicatr-rr
of
and efficHighly
I
I
28
6.4
Check thatstaf at
this level continue to be engaged in the sensitisation/ mobilisation ofrelevantdecision makers in there area
of
7.1
Check whether the cost implications of each CDTI related activity (monitoring/ supervision, training/rnobilisation, Mectizan distribution) are quantified in the yearly budgetfor the heatth district/ LGA
of
7.2
Checkwhether appropriate and adequate amounts are budgetedfor
the planned CDTI related activities ofeffectiveness and7
.3
Check whether funds to cover these costs are increasingly being supplied from district/ LGA resourcesof
1.4
Cteckif
r.z case of a deficit between estimated costs and the amount provided by the government, ,s made to meetit
of effectiveness and attitudeStaf
routinely identify situations where decision makers lack information obout/ commitment to CDTI, and undertake activities to inform and persuade these persons.Staffhave promotional materials at their disposal
for
thb purpose(liers,
posters etc.).Findines:
Hold annual stake holders workshops involve all political decision makers from LC V, LC
IV
andLV lll
levels.
Apparently inform political staff at other times as we ll, but no evidence.
No appropriate rnaterial seen.
Is this critcrion
for
sustainability being tulfilled?Fully Highly Slightly Not at all Not applicable
costs
for
each CDTI related activity in the year plan should be clearly spelt out in the budget.Recarrent and
capital
costs (if any) should be separated in the budget.The Findines:
CDTI activities within the district budget are now incorporated under PHC outreach activities. Specific activities are not delineated.
A
separate budgetlbr
CDTI activities is used for outside funding.Is this criterion
for
sustainability being tulfilled?Fully Highly Slightly Not at all Not applicable
The amounts budgeted should be neither excessive nor too small - managers should be able to
justifi
the needfor
each amount,in
relation to:.
The outcomaresultingfrom
the previous year's CDTIupenditure
'
The cost ofsimilar
activitiesfor
otlter programmes.Findines:
Amounts budgeted are hidden in the budget at each
level.
No specific plan seen for amount budgeted.Is this criterion
for
sustainability being tulfilled?Fully Moderately Slightly Not at all Not applicable
t
The relative contributions of thedistict/
LGA and otherprtnat
should be clearly spelt out.'
Theproportbn
provided by thefficial
healthservice should be the major one by now.
'
This proportion offunds should be increasing yeqrty.Findines:
Because of the nature of the budgeting,
it
is impossible to determine how much money is allocated for CDTI activities. Allocations are made on the basis of goodwill
and perceived need overall.Is this criterion
for
sustainability being tulfiIled?Fully Highly Moderately Not at all Not applicable
'
Manogement should be aware of the size of the shonfall, and have specific and realistic plans to bidge it.'
If it is planned that non-government sourcesof
fundinz are zo be used after APOC funding ends, wrinet commitment
for
this should have been obtained at the highest level in these donor organisations (e.g. a new Memorandum o.f Undersnnding).Findines:
Short
Iall
lras been taken u1t bvAl,(X'arrtj N(il)().
I)oliticians speak ol'yrossibilitv to takc up sltortl'ull ar t'rrtl
ol'AI'}O('Iirnding.
hut lto cvi(lence thus lhr.No Ilrrn conrrnilntcnl li'onr anv outsitle lirnrle r to car r v
c ()sl s.
Is this cn'<rion fr-'r s ustainabi li ty being tulrilled?
Fully Highly Moderately Not at all Not applicable rModpratb.lY
iHiglily
7.5
Check whether CDTI funds in the heqlth district/ LGA budget areeficiently
managed (indicatorof
effectiveness and
8.1
Checkif
there issuficient
transportfor
necessary visils to the sub-district levelfor
CDTI relatedactivities
of
8.2
Checkrf
trips/ journeys undertakenfor
routine CDTI purposes are inlegrated with those madefor
other
or of
and8.3
Checkif
the made available CDTI isof
9. Human resources '
r..',., :t,,,',*?i*l$S$ffi#
9.1
Check z'hether the health district/ LGA team is skilled and htov,ledgeable, regarding the CDTIin
its area tion indicator of effectivenessFindines:
Spending in the district is based on integrated funds. No specific budget itenrs
The budget holder should use a control system with the following elements:
:
Approval ofeach item ofetpenditure.
Allocation of expenditure against specific budget headings.
Regular calculation ofresidual amounts under budget headings.Is this criterion for sustainability beins tulfiUed?
Fully
Highly Moderately Slightly Not atall
There should be no reports
offailure
to undertake necessary CDTI qctivities at sub-district level, due to transport not being available or afordable.Transport provided by the central level should no longer be
usedfor
routine CDTI activities atLGA/
district level.
Checklis t of activities : monitoring/ supervisio n,
trainins/ mobilis ation, Mectizan distribution
I Findines:
No reports of laih.rles due to insufficient transport.
Transporl pool is integrated although there is a motor cycle provided by APOC, all are allocated to individuals not pro.jecls.
Is this criterion for sustainability being fulfilled?
Fully
Moderately Slightly Not at all Not applicableWhere
CDTI
is involved. trips should be authorised/undertaken
for
more than one purpose.Means of
rransport
provided by specificprogrammes should be usedfor other programmes as well.
ChecHist
of
activities : monitoring/ supervision, trainins/ mobilisation, Mectizandistibution
Findinss:
Most Onchocerciasis activities involve specific trips
All
vc'hicles poolcd.Is this criterion
for
sustainability beingtulfilled?
Fully
Moderately Slightly Not at all Not applicableuuLc,
a
I
Trips
madefor
CDTI purposes should be properly authorisedin writing bylhe
relevantfficial.
Each
trip undertakenfor
CDTI purposes should be recordedin
a log book.Findines:
At this level there is no control of vehicle activity
Is this criterion for sustainability being tulfrlled?
Fully
Highly Moderately Slightly Not atall
LGA/ health
dutrict
team members should have enough knowledge andskill
to undertakeall
the key CDTI activities themt.elves, without help :'
Planning'
Training nnd sensilisation/ mobilisation'
Mectizanr,rdering/
distribution'
MonitorinT/super-vision.Findinss:
-T'hc ()rrclrott'rcrrsi: slall'at
tlistrict lcrcl
appcar to bc u'cl I lrairtt'<l urttl k ntrrvlcrlccablcModerately Slightly Not at all Not applicable
I
Is this criterion
for
sustainability Highly tulfilled?:I,Ii,Bhh
30
9.2
Check whether personnel at the heahh district/ LGA level is stable,and whetherprovision is made'for
onCDTI
skills when a trained moves ofeffectivenessStaf
shoulel remain in onepostfor
at leastfive years.There should be immediate training (in CDTI)
of
new, unskilled district/ LGA staffmembers who have CDTIrespory!ibilities.
Findines:
Stability of staff is not guaranteed although there is more than one person within the district able to manage CDTI activities.
NOC staff undertake training of staffat this level.
Is ttris criterion for sustainability beigg tulfilled?
Fully ;.. .. Moderately Slightly Not at all Not applicable