Stanislav Hudcovský
Managing Director for Development, Investments and International Cooperation
Bratislava, 10.
Bratislava, 10.- -12. October, 2005 12. October, 2005
Development Development of the Slovak
of the Slovak E E nergy nergy
T T rans rans s s mission mission S S ystem ystem
Table of Content
Impacts of Impacts of EBO V1 EBO V1 decommissioning o
decommissioning o n TS n TS SR SR
Pri Pri mary mary a a nd nd se se condary condary consequences of EBO V1 consequences of EBO V1
decommissioning decommissioning
Solutions Solutions and a nd measures measures in in T T S SR S SR
R 400 kV Kri R 400 kV Kri ž ž ovany ovany project
project
Impacts of the Impacts of the EMO 3,4 EMO 3,4 commissioning
commissioning
Strat Strat egy of egy of TS SR TS SR development
development
Transmission System of the Slovak
Republic 2005
Impacts of the EBO V1 Decommissioning on ES SR
The EBO V1 decommissioning during 2006 - 2008 ⇒ loss of 2x440 MW in Križovany node (220 kV system)
880 MW loss
primary consequences
secondary consequences
Primary Consequences of the EBO V1 Decommissioning
d d irect impact irect impact on on ES SR ES SR e e lectric lectric components components in in term of the dispatch
term of the dispatch control control
deficit of power output from EBO V1 unit (Križovany),
deficit of power in 220 kV nodes (Senica, Považská Bystrica, Bystričany),
influence on available volume of ancillary services for secondary control,
change of the ES SR configuration,
increase of the cross-border flows,
decrease of the 220 kV system operation
reliability
Secondary Consequences of EBO V1 Decommissioning
indirect impact indirect impact on on ES SR ES SR electric components electric components
necessity to relieve maintaining reserve output of 400/220 kV coupling to preserve current transmission
capacity
¾ substation Medzibrod ⇒ evaluation of its next usage at 220 kV voltage level,
¾ reinforcement of Lemešany node, resp. the whole Eastern Slovakia,
¾ technical lifetime of 220 kV lines V283, V274, V271, V275 (average age more than 40 years)
220 kV system ? ? 400 kV system
Solutions and Measures in TS SR (1)
re re c c onfigur onfigur ation ation a a nd nd re re construction construction of 220 kV system part to 400 kV voltage level due to loss of sources working to 220 kV system,
implementation of the direct direct transform transform ation ation 400/110 kV instead the indirect transformation 400/220/110 kV in relevant nodes,
power supplying of Kri Križ žovany ovany node locality from 400 kV system with preserving 220/110 kV transformer as
a coupling between the voltage levels for eventual self – consumption of EBO V1 and EBO A1 supplying,
power supplying Medzibrod Medzibrod node locality from 400 kV
system and transformation change from 220/110 kV to
400/110 kV,
Solutions and Measures in TS SR (2)
substation Leme Leme š š any any 400 kV expansion and 400 kV Leme Leme š š any any – – Moldava Moldava line construction with possible system loop to USSK node,
increase of transmission transmission capacity capacity for import from Czech Republic, Poland and eventually from Ukraine in future,
development development plans plans focused on 400 kV system construction,
invest invest ments ments with a huge bulk of finance for SEPS, a.s.,
financial support from E E U U funds funds (BIDSF and
TEN-E projects)
R 400 kV Križovany
Substation of New Generation
R 400 kV Križovany Project main characteristic
Conception Conception of the of the re re construction construction of the whole
substation planned for 09/2002 – 10/2010 period in continuous operation of substation has devided into 4 phases.
13 fields (width 18 m, length 93 m) 3 main a 1 secondary bus bars 2 TR 400/110 kV – 350 MVA compensation chokes 2x45 MVAr
pantographic disconnector ecologic equipment new electric devices
new control and information system possibility of remote control
New conception
R 400 kV Križovany Project financing
costs costs more than more than 1 mld. Sk 1 mld. Sk partly financed by SEPS, a.s.
and partly by the EC via BIDSF
R 400 kV Križovany Recontruction Phases
Pphase 1 Phase 2
Pphase 3 Phase 4
09/2002 ⇔ 09/2003
11/2004 ⇔ 06/2006 10/2005 ⇔ 12/2006
02/2006 ⇔ 09/2008
03/2009 ⇔ 10/2010
part 1 part 2
Impacts of the EMO 3,4 Commissioning
New power source 2x500 MW soonest in the year 2012
¾ necessity of solving the power output of new units EMO 3,4 EMO 3,4 (2x500 MW)
(2x500 MW) to TS SR,
¾ necessity of solving the power output resulting from EMO 1,2EMO 1,2 power increase till the year 2008 (cca. 2x490 MW)
it is needed to solve and to review the power output to TS SR for EMO 1,2,3,4
EMO 1,2,3,4 as a whole aggregate
there is an assumption of power output to V.Ďúr substation, (specification after recieving complete details from investor)
necessity to process a new studystudy of new source effectof new source effect to TSto TS SRSR for existing EMO 1,2,3,4 power output
To take measure on sufficiency of current solution, resp. to adopt measures, while complete data needed for study are not yet available for SEPS,a.s.
¾ SEPS,a.s. consideres and planns its investment plan construction of new V.V. ĎúĎúr r –– GabčGabčííkovokovo 2x400kV 2x400kV line andline newnew GabčGabčíkovo íkovo substation
substation also concerning another contingencies and TS SR needs not only linked to EMO.
Strategy of TS SR Development (1)
measuresmeasures inin ES SRES SR due to EBO V1 decommissioning , resp. the commissioning of the further EMO units,
reinforcement of internal and cross-border systems,reinforcement
coordinatedcoordinated pplanninglanning of transmission in order to optimal transfer capacity usage,
observating the safetysafety andand qualityquality electricity supply,
the task of investmentsinvestments ffinancinginancing with usage of EU funds,
provision of sufficient bulk of ancillary services,ancillary services
to focuse on higher voltage levelvoltage level 400 kV construction,400 kV construction
implementation of new control system,control system
Strategy of TS SR development (2)
complexcomplex recontructionsrecontructions of electric substations in sequence with implementation the remote control,
putting the new generation devicesnew generation devices (reliable, ecologic, maintenance-free),
minimaliminimalisation ofsation of layofflayoff devices for transsmision in term of maintenance,
constraint of rising new congestionscongestions following the system connection expansion,
preparation the TS SR for new trendsnew trends ( volubile output,
developing market with electricity and increased claims on safety and reliability),
obligation fullfilmentobligation fullfilment resultating from memberships in international assotiations.