JANUARY 2022
Porte Maillot:
Worksite Update
Porte Maillot worksite………....03 Porte Dauphine worksite………...06 EOLE technical base camp footprint……....10 Worksite at former exit ramp..….…...13 Access fromPorte de Champerret…...15
Contents
2
1
Porte Maillot
Worksite
4
Porte Maillot Worksite
Until the beginning of March 2022:
▪ Boulevard Gouvion St Cyr’s southbound lane open
All vehicles taking Boulevard Gouvion St Cyr’s southbound lane will be able to turn right and pass directly in front of the
Palais des Congrès de Paris.
Information subject to change, pending construction works (source: SPL).
Porte Maillot Worksite
Starting in early March 2022:
▪ Closure of Boulevard Gouvion St Cyr’s southbound lane
▪ Reopening of Boulevard Gouvion St Cyr’s northbound lane
Boulevard Gouvion St Cyr will once again be accessible from Boulevard Pereire
Information subject to change, pending construction works (source: SPL).
2
Porte Dauphine
Worksite
Porte Dauphine Worksite
From 28 January to the end of August 2022:
▪ Maréchal-de-Lattre-de-Tassigny worksite
▪ Porte Maillot will not be accessible from Boulevard Amiral Bruix
Information subject to change, pending construction works (source: Mission Tramway).
8
Porte Dauphine Worksite
From 1 January 2022 until the end of August 2022:
▪ Porte Maillot will be inaccessible from Boulevard Amiral Bruix
To access the Palais des Congrès
from Porte Dauphine: take Avenue Foch and then Avenue Malakoff.
For more information, please see next slide.
Information subject to change, pending construction works (source: SPL).
Porte Dauphine Worksite
Route to the Palais des Congrès de Paris from Porte Dauphine:
valid from 1 January 2022 until the end of August 2022
Loading dock acess
Indigo Porte Maillot car park entrance
Information subject to change, pending construction works.
3
EOLE and T3
Boulevard Pershing:
Technical Base Camp Footprint
Boulevard Pershing:
Technical Base Camp Footprint
Information subject to change, pending construction works (source: Eole).
12
HGV Access to/from Boulevard Pershing
EOLE Technical Base Camp
4
Indigo Car Park:
Worksite at Former Exit Ramp
14
Worksite at Former Exit Ramp
Provisional works schedule:
▪ February 2022: preparatory works and worksite setup
▪ March 2022: removal and demolition of ramps and walls
▪ April 2022: creation and waterproofing of reinforced concrete surface for T3 tram
▪ Early May 2022: waterproofed concrete surface ready for T3 tram (completion: 1 June 2022 at the latest)
Further work at this site where the T3 tramway crosses the concrete surface will resume in summer 2022. The worksite will be restricted to the perimeter of the former cement hopper.
5
Recommended Access From
Porte de Champerret
16
Map: Porte de Champerret – Recommended Access
South North
From north ring road
From south ring road
PORTE DE CHAMPERRET EXIT
Satellite View:
Porte de Champerret – Recommended Access
Porte de Champerret exit from
périphérique Sud
Espace Champerret Acess to
périphérique Sud
Porte des Ternes/Maillot exit
Palais des Congrès de Paris
18
Satellite View:
Loading Dock Entrance and Exit
HYATT SHUTTLES LOADING DOCK
ENTRANCE
TAXIS HYATT
LOADING DOCK EXIT
LOADING DOCK EXIT HOTEL HYATT EXIT
DISCLAMER
This presentation has been prepared and provided by Viparis for information purposes only. Every reasonable precaution has been taken to ensure that the information contained herein is neither false nor misleading, but no representation is made as to its accuracy or completeness.
The elements in this presentation may be changed or amended without notice, and it is therecipient’s responsibility to ascertain their fixed nature before starting a project.
Viparis may not be held liable for losses or damages of any kind resulting from the use of part or all of this presentation; only contractual agreements may be enforced against it.
CLAUSES DE RÉSERVE
« Cette présentation a été préparée et remise par Viparis à titre d’information seulement. Toutes les précautions raisonnables ont été prises pour s’assurer que l’information contenue dans ce document n’est ni fausse ni trompeuse, mais aucune déclarationn’est faite quant à leur exactitude ou leur exhaustivité. Les éléments communiqués dans cette présentation sont sujets à évolu- tion ou modification sans préavis et il
incombe à son destinataire d’en vérifier l’intangibilité avant d’engager un projet.
Viparis n’assume aucune responsabilité pour toute perte ou dommage de toute nature résultant de l’utilisation de tout ou partie de cette présentation; seuls des documents contractuels pouvant lui être opposés. »