Explanatory Note on the LFC Means November 20, 2019
Texte intégral
Documents relatifs
On the on-going discussion on the availability of non-contracted balancing energy bids for mFRR, where Elia does not want to take them into account, Febeliec refers to its
In comparison with the T&C BSP FCR version 1 1 that was comprised of the General Conditions, the T&C FCR CIPU (replacing the GFA FCR CIPU) and the T&C FCR
In the new aFRR design, the aFRR energy bids are activated based on a merit order mechanism and Elia will no longer apply a volume cap. If no limitations on the activation price
Elia wants to remind the BSPs that the availability test is only failed if the aFRR Power supplied is inferior (respectively superior) to the aFRR Capacity Requested for more
II.10.14 In case the total volume offered as mFRR Standard in the mFRR Energy Bids (respectively mFRR Flex) submitted for a quarter-hour is not equal to the corresponding
Elia adds the reason “Flexibility for fulfilment of BRP obligations” to the list of reasons accepted by Elia for (partial) rejection of activation of non-contracted mFRR energy
For the purpose of this analysis, Elia will compare the results of the positive and negative FRR needs based on the methodology in the LFCBOA and compare this with the
First of all, article 152(2)k specifies that for the synchronous area CE, the reduction of the positive and negative reserve capacity on FRR of a LFC block is limited to the