Febeliec answer to the consultation relating to the modifications to the ARP contract as proposed by Elia

Febeliec does not have any specific comments on this consultation. However, Febeliec would like to make a general comment towards all previous consultations, the current consultation and

potentially future consultations on the ARP-contract and the work on-going on the BRP and BSP contracts and all related Terms and Conditions, where Febeliec hopes that Elia will take into account all the received comments in its elaboration of the latter documents and will bring them in line with the latest discussions on and evolutions of the ARP-contract.

Références

Documents relatifs

The determination of a requested reactive power volume in the context of the service for reactive power and voltage control is also coherent with the

The signature of a CIPU contract is required to participate to the black-start service because the outage planning, provided to Elia through CIPU procedures, is necessary

Nevertheless, Febeliec remains very strongly convinced that in order for the CRM to lead to a robust outcome (e.g. avoid issues related to lack of competition), it is necessary

Febeliec especially regrets this for units smaller than 1MW connected to the public grid at voltage levels of more than 110 kV, as even in 5 years there impact, as acknowledged

On the deterministic frequency deviations, Febeliec urges strongly to conduct a full CBA, clearly indicating the involved costs and benefits of all proposed alternative scenarios,

Febeliec would like to thank the CREG for the consultation on the proposal of Elia for the modification of the flow-based day-ahead market coupling in CWE on the treatment of

The Banks intend to offer the following the "Revised Offer", through their acquisition vehicle RFS Holdings subject to certain pre-conditions: €38.40 per ABN AMRO Share, 13.7% above

Febeliec answer to the CREG consultation on the request for derogation from Elia on the minimum level of capacity to be made available for cross-zonal trade.. Febeliec would to