Université Paris-Dauphine, 31 January 2013
Short-term and Long-Term System Effects of
Intermittent Renewables on Nuclear Energy
and the Electricity Mix
Jan-Horst Keppler and Marco Cometto
Université Paris-Dauphine, 31 January 2013
OECD NEA System Effects Study
Key Issues
3. Institutional frameworks, regulation and policy
conclusions to enhance the sustainability, flexibility and security of supply of power generation and
enable coexistence of renewables and nuclear power in decarbonising electricity systems
2. Quantitative estimation of system effects of different generating technologies
o Costs imposed on the electricity system above
plant-level costs
o Total system-costs in the long-run
o Impact of intermittent renewables on nuclear energy
and other generation sources
1. Interaction between renewable, nuclear power and
Université Paris-Dauphine, 31 January 2013
“System costs are the total costs above plant-level costs to supply electricity at a given load and given level of security of supply.”
• Plant-level costs
• Grid-level system effects (technical externalities)
o Grid connection
o Grid-extension and reinforcement
o Short-term balancing costs
o Long-term costs for maintaining adequate back-up capacity
• Impact on other electricity producers (pecuniary externalities)
o Reduced prices and load factors of conventional plants in the short-run
o Re-configuration of the electricity system in the long-run
• Total system costs
o Take into account not only the costs but also the benefits of integrating new capacity (variable
costs and fixed costs of new capacity that could be displaced)
o Other externalities (environmental, security of supply, cost of accidents, …)
System Effects – An Introduction
Plant-level costs
Grid-level costs
Université Paris-Dauphine, 31 January 2013
The Short-run and the Long-run
• Crucial importance of the time horizon, when analyzing adequacy/back-up costs and
impacts on dispatchable generators (no issue for grid costs or balancing costs):
•
Adequacy/back-up costs :
o In the short-run (ex post), in a system where existing capacity reliably covers peak
demand, there are no back-up costs for new variable renewable capacity.
o In the long-run (ex ante), variable renewable capacity due to its low « capacity credit »
demands dedicated back-up, which is not commercially sustainable on its own.
•
Impacts on dispatchable generators
o In the short-run, the pecuniary externalities of subsidized, variable renewables
(reduced electricity prices and load factors) will over-proportionally affect technologies with high fixed costs such as CCGTs.
o In the long-run, the structural re-composition of residual dispatchable capacity will
over-proportionally affect technologies with high fixed costs such as nuclear. Issue for investors and researchers: when does the short-run become the long-run?
Université Paris-Dauphine, 31 January 2013
Methodology:
Long-term optimal mix (I)
Yearly load duration curve
0 10 20 30 40 50 60 70 80 90 100 0 1000 2000 3000 4000 5000 6000 7000 8000 P o w e r (G W )
Utilisation time (hours/year) 0 20 40 60 80 100 E le ct ri ci ty d e m a n d ( G W )
Electricity demand in France (2011)
• Simply obtained by ordering demand from highest to lowest.
• The curve shows the number of hours that electricity demand is higher than a certain level. • Electricity consumed is the integral of load duration curve.
Université Paris-Dauphine, 31 January 2013 0 100 200 300 400 500 600 700 800 900 1000 0 1000 2000 3000 4000 5000 6000 7000 8000 A n n u a l co st ( U S D /k W /y e a r)
Utilisation time (hours/year)
Gas (OCGT) Gas (CCGT) Coal Nuclear Optimal
OCGT CCGT Coal Nuclear
Methodology:
Long-term optimal mix (II)
Université Paris-Dauphine, 31 January 2013
Methodology:
Long-term optimal mix (III)
0 10 20 30 40 50 60 70 80 90 100 0 1000 2000 3000 4000 5000 6000 7000 8000 P o w e r (G W )
Utilisation time (hours/year)
OCGT: electricity generated CCGT: electricity generated Coal: electricity generated Nuclear: electricity generated Yearly Load 0 100 200 300 400 500 600 700 800 900 1000 0 1000 2000 3000 4000 5000 6000 7000 8000 A n n u a l c o st ( U S D /k W /y e a r) Gas (OCGT) Gas (CCGT) Coal Nuclear Optimal 0 10 20 30 40 50 60 70 80 90 100 C a p a ci ty ( G W ) Enucl Cnucl Ecoal Eccgt Eocgt Cocgt Cccgt Ccoal • The optimal generation mix
obtained is the one that
minimises the generation cost for meeting a given yearly load duration curve.
• The cost/MWh depends upon the shape of the load duration curve.
Fixed costs Variable costs LCOE USD/MW/year USD/MWh USD/MWh
OCGT 43.5 113.8 118.7
CCGT 96.1 76.4 87.4
Coal 212.8 49.8 74.1
Université Paris-Dauphine, 31 January 2013
Methodology: calculating a residual
load duration curve with VaRen
Residual load duration curve (wind at 30%)
0 20 40 60 80 100 E le ct ri ci ty d e m a n d ( G W )
Electricity demand in France (2011)
• Represents the load curve seen by the other dispatchable generators after the integration of low-marginal cost wind.
• Statistical analysis (Monte Carlo with 650 runs) • Non-parallel shift of the residual load duration
curve 0 10 20 30 40 50 60 70 80 90 100 0 1000 2000 3000 4000 5000 6000 7000 8000 P o w e r (G W )
Utilisation time (hours/year)
Yearly load
Residual load: wind at 30% penetration
+ 0.0% 0.5% 1.0% 1.5% 2.0% 2.5% 3.0% 3.5% 4.0% 4.5% 5.0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% P ro b a b il it y ( % )
Wind load factor
Université Paris-Dauphine, 31 January 2013
Short-run impacts
In the short-run, renewables with zero marginal costs replace technologies with higher marginal costs, including nuclear as well as gas and coal plants. This means:
• Reductions in electricity produced by
dispatchable power plants (lower load factors, compression effect).
• Reduction in the average electricity price
on wholesale power markets, merit order
effect (by 13-14% and 23-33%).
Wind Solar Wind Solar Gas Turbine (OCGT) -54% -40% -87% -51%
Gas Turbine (CCGT) -34% -26% -71% -43%
Coal -27% -28% -62% -44%
Nuclear -4% -5% -20% -23%
Gas Turbine (OCGT) -54% -40% -87% -51%
Gas Turbine (CCGT) -42% -31% -79% -46% Coal -35% -30% -69% -46% Nuclear -24% -23% -55% -39% -14% -13% -33% -23% Lo a d l o ss e s P ro fi ta b il it y lo ss e s
Electricity price variation
10% Penetration level 30% Penetration level • Declining profitability especially for
gas (nuclear is less affected).
• Carbon emissions are considerably
reduced (by 30% to 50%)
• No sufficient economical incentives
to built new power plants.
• Security of supply risks as fossil
plants close. 0 10 20 30 40 50 60 70 80 90 100 0 1000 2000 3000 4000 5000 6000 7000 8000 P o w e r (G W )
Utilisation time (hours/year)
Gas (OCGT): Lost load Gas (CCGT): Lost load Coal: Lost load Nuclear: Lost load Yearly Load Residual load
Université Paris-Dauphine, 31 January 2013
Long-run impacts on the
optimal generation mix
• New investment in the presence of renewable production will change generation structure.
• In the absence of countervailing measures (carbon taxes), nuclear power will be displaced by a more
carbon-intensive mix of renewables and gas.
• The cost for residual dispatchable load will rise as technologies more expensive per MWh are used.
Université Paris-Dauphine, 31 January 2013
Long-term effects:
cost for providing the residual load
We compare two situations: the residual load duration curve for a 30% penetration of
fluctuating wind (blue curve) and 30% penetration of a dispatchable technology (red curve).
0 10 20 30 40 50 60 70 80 90 100 0 1 000 2 000 3 000 4 000 5 000 6 000 7 000 8 000 P o w e r (G W )
Utilisation time (hours/year)
Wind surplus Wind shortage Load duration curve Residual load curve - wind Residual load curve - dispatchable
85.5 USD/MWh
81.8 USD/MWh
∆= +3.7 USD/MWhResidual
Université Paris-Dauphine, 31 January 2013 20% 30% 40% 50% 60% 70% 80% 90% 100% 0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50% E le ct ri ci ty v a lu e ( % o f a f la t b a n d ) Penetration level (%)
Electricity value - dispatchable
Electricity value - wind
Electricity value - solar
20% 30% 40% 50% 60% 70% 80% 90% 100% 0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50% E le ct ri ci ty v a lu e ( % o f a f la t b a n d ) Penetration level (%)
Electricity value - dispatchable Electricity value - wind
Marginal electricity value - wind Electricity value - solar
Marginal electricity value - solar
Value of an intermittent generation source
from a system viewpoint
We can look at the impact of the intermittency from a different perspective:
• Cost for the whole electrical system (externality)
• Value of an intermittent generation source (as seen by the system)
Université Paris-Dauphine, 31 January 2013
The notion of capacity credit
The capacity credit is “the amount of additional peak load that can be served due to the addition of a power plant, while maintaining the existing level of reliability”.
0 10 20 30 40 50 60 70 80 90 100 0 1000 2000 3000 4000 5000 6000 7000 8000 P o w e r (G W )
Utilisation time (hours/year)
Yearly load
Residual load: wind at 30% penetration
In st a ll e d w in d c a p a ci ty ( 7 8 G W )
Université Paris-Dauphine, 31 January 2013 70 75 80 85 90 95 0 10 20 30 40 50 60 70 80 90 100 P o w e r (G W )
Utilisation time (hours)
Yearly Load Curve Residual load curve
Dispatchable generation capacity that could be replaced based on averaged values.
CC=5,8 GW / 77,9 GW = 7,5% 70 75 80 85 90 95 0 10 20 30 40 50 60 70 80 90 100 P o w e r (G W )
Utilisation time (hours)
Yearly Load Curve Residual load curve Residual load curve - Max Residual load curve - Min
Dispatchable generation capacity that could be replaced based on averaged values.
Dispatchable generation capacity that can be effectively replaced (IEA).
Residual load curve corresponding to a minimal wind production.
Residual load curve corresponding to a maximal wind production. 1 σ
CC=5,9%
Residual load duration curves allow for simple and reliable estimation of the capacity credit.
• Capacity credit is calculated using complex probabilistic techniques (LOLP) and requires a
sophisticated modeling of the electricity system.
Methodology: estimates of capacity credit
using residual load duration curves
Université Paris-Dauphine, 31 January 2013
• Six countries, Finland, France, Germany, Korea, United Kingdom and USA analysed
• Grid-level costs for variable renewables at least one level of magnitude higher than for
dispatchable technologies
System Effects of Different Technologies:
Estimating Grid-level Costs
o Grid-level costs depend strongly on country,
context and penetration level
o Grid-level costs are in the range of 15-80
USD/MWh for renewables (wind-on shore lowest, solar highest)
o Average grid-level costs in Europe about
50% of plant-level costs of base-load technology (33% in USA)
o Nuclear grid-level costs 1-3 USD/MWh
o Coal and gas 0.5-1.5 USD/MWh.
0 100 200 300 400 10% 30% 10% 30% 10% 30% 10% 30% 10% 30% 10% 30%
Nuclear Coal Gas On-shore wind Off-shore wind Solar
To ta l co st [ U S D /M W h ]
Grid-level system costs
Plant-level costs
Technology
Penetration level 10% 30% 10% 30% 10% 30% 10% 30% 10% 30% 10% 30% Back -up Costs (Adequacy) 0.00 0.00 0.05 0.05 0.00 0.00 6.03 7.38 5.71 7.67 15.88 18.04
Balancing Costs 0.53 0.35 0.00 0.00 0.00 0.00 4.19 8.34 4.19 8.34 4.19 8.34
Grid Connection 1.71 1.71 0.94 0.94 0.51 0.51 6.24 6.24 18.68 18.68 13.71 13.71
Grid Reinforcement and Extension 0.00 0.00 0.00 0.00 0.00 0.00 2.23 6.28 1.51 3.82 4.46 13.55
Total Grid-Level System Costs 2.24 2.05 0.99 0.99 0.51 0.51 18.69 28.24 30.11 38.51 38.25 53.64
System Costs at the Grid Level (average of 6 countries - USD/MWh)
System Costs at the Grid Level [USD/M Wh]
Université Paris-Dauphine, 31 January 2013
The Total Costs of Electricity Supply
for Different Renewables Scenarios
• Total costs of renewables scenarios are
large, especially at 30% penetration levels:
o Plant-level cost of renewables still
significantly higher than that of dispatchable technologies.
o Grid-level system costs alone are
large, representing up to 67% of the increase in unit electricity costs.
Ref. Conv. Mix Wind on-shore Wind off-shore Solar Wind on-shore Wind off-shore Solar
Total cost of electricity supply 80.7 86.6 91.3 101.2 105.5 116.9 156.2
Increase in plant-level cost - 3.9 7.8 16.9 11.6 23.3 50.6
Grid-level system costs - 1.9 2.8 3.6 13.2 12.9 24.9
Cost increase - 5.8 10.6 20.4 24.8 36.2 75.4
Total cost of electricity supply 98.3 101.7 105.6 130.6 111.9 123.6 199.4
Increase in plant-level cost - 1.5 3.9 26.5 4.5 11.7 79.6
Grid-level system costs - 1.9 3.4 5.8 9.1 13.6 21.5
Cost increase - 3.4 7.3 32.3 13.6 25.3 101.1
Total cost of electricity supply 72.4 76.1 78.0 88.2 84.6 91.5 123.7
Increase in plant-level cost - 2.1 4.2 14.3 6.2 12.5 42.8
Grid-level system costs - 1.6 1.4 1.5 6.0 6.5 8.5
Cost increase - 3.7 5.6 15.7 12.2 19.1 51.2 G e rm a n y U K U S A
Total cost of electricity supply [USD/MWh]
10% penetration level 30% penetration level
• Comparing total annual supply costs
of a reference scenario with only dispatchable technologies with six renewable scenarios (wind ON, wind OFF, solar at 10% and 30%)
o Takes into account also fixed
and variable cost savings of displaced conventional PPs
Université Paris-Dauphine, 31 January 2013
New Markets for New Challenges
A. Markets for short-term flexibility provision
For greater flexibility to guarantee continuous matching of demand and supply exist in principle four options that should compete on cost:
1. Dispatchable back-up capacity and load-following
2. Electricity storage
3. Interconnections and market integration
4. Demand side management
So far dispatchable back-up remains cheapest.
The integration of large amounts of variable generation and the dislocation it creates in electricity markets requires institutional and regulatory responses in at least three areas:
B. Mechanisms for the long-term provision of capacity
There will always be moments when the wind does not blow or the sun does not shine.
Capacity mechanisms (payments to dispatchable producers or markets with supply obligations for all providers) can assure profitability even with reduced load factors and lower prices.
C. A Review of Support Mechanisms for Renewable Energies
Subsidising output through feed-in tariffs (FITs) in Europe or production tax credits (PTCs) in the United States incentivises production when electricity is not needed (including negative
prices). Feed-in premiums, capacity support or best a substantial carbon tax would be
Université Paris-Dauphine, 31 January 2013
Université Paris-Dauphine, 31 January 2013
Methodology: long-term optimal mix
Residual load duration curve (solar at 30%)
0 20 40 60 80 100 E le ct ri ci ty d e m a n d ( G W )
Electricity demand in France (2011)
• Represents the load curve seen by the other dispatchable generators after the integration of low-marginal cost solar.
• Statistical analysis (Monte Carlo with 650 trials) • *** + 0 10 20 30 40 50 60 70 80 90 100 0 1000 2000 3000 4000 5000 6000 7000 8000 P o w e r (G W )
Utilisation time (hours/year)
Yealy load Residual load 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 0 3 :0 0 0 9 :0 0 1 5 :0 0 2 1 :0 0 0 3 :0 0 0 9 :0 0 1 5 :0 0 2 1 :0 0 0 3 :0 0 0 9 :0 0 1 5 :0 0 2 1 :0 0 0 3 :0 0 0 9 :0 0 1 5 :0 0 2 1 :0 0 0 3 :0 0 0 9 :0 0 1 5 :0 0 2 1 :0 0 0 3 :0 0 0 9 :0 0 1 5 :0 0 2 1 :0 0 0 3 :0 0 0 9 :0 0 1 5 :0 0 2 1 :0 0 0 3 :0 0 0 9 :0 0 1 5 :0 0 2 1 :0 0 0 3 :0 0 0 9 :0 0 1 5 :0 0 2 1 :0 0 0 3 :0 0 0 9 :0 0 1 5 :0 0 2 1 :0 0 0 3 :0 0 0 9 :0 0 1 5 :0 0 2 1 :0 0 0 3 :0 0 0 9 :0 0 1 5 :0 0 2 1 :0 0 0
January February March April May June July August September October November December
S o la r lo a d f a ct o r
Solar load factor - yearly insolation data and variability
Maximal "Solar radiation" Minimal
Université Paris-Dauphine, 31 January 2013
Impacts on CO
2emissions
and electricity price
In the short-run, renewables replace technologies with higher marginal cost, i.e. fossil-fuelled
plants emitting CO2.
• Electricity market prices are significantly reduced (by 13-14% and 23-33%)
• Carbon emissions are considerably reduced (by 30% to 50%).
In the long-run, low-marginal cost renewables replace base-load technology.
• No changes in electricity market prices at penetration levels < 25% (time-weighted prices).
• The long-term effect on CO2 emissions depends on the base-load technology displaced
(nuclear or coal):
o If there was no nuclear on the generating mix, renewables will reduce CO2 emissions.
o If nuclear was part of the generating mix, CO2 emissions increase.
Reference
Wind Solar Wind Solar
[%] [%] [%] [%]
Short-term -31% -29% -66% -44%
Long-Term 2% 4% 26% 125%
Short- and long-term CO2 emissions
10% Penetration level 30% Penetration level
[Mio tonnes of CO2]
Université Paris-Dauphine, 31 January 2013
Cost of providing residual load
10% penetration 30% penetration W in d S o la r
+4.3 USD/MWhRen +8.7 USD/MWhRen
+25.8 USD/MWhRen
Université Paris-Dauphine, 31 January 2013
Value of intermittent generation:
a simple example for a flat band
0 10 20 30 40 50 60 70 80 90 100 P o w e r (G W )
Utilisation time (hours/year)
Load duration curve
Residual load curve - ideal generator
• The value of the electricity produced by the ideal generator is calculated as the difference between the cost of supplying the original load duration and the residual curve.
• The value of the flat band for the system is equal to the cost of base-load technology.
A generator providing a flat power band (30% of the electricity)
Result
• A parallel shift on the load curve.
• The flat power band replaces base-load technology.
• No changes in the capacities and electricity production of medium- and peak-load
technologies.
Total cost Specific cost
[Bil. USD] [USD/MWh]
Original load curve 37.18 78.20
Residual curve 27.32 81.96
Université Paris-Dauphine, 31 January 2013 0 10 20 30 40 50 60 70 80 90 100 0 1000 2000 3000 4000 5000 6000 7000 8000 P o w e r (G W )
Utilisation time (hours/year)
Yearly load
Residual load: wind at 30% penetration
Total cost Specific cost
[Bil. USD] [USD/MWh]
Original load curve 37.18 78.20
Residual curve 28.60 85.79
Value of wind at 30% PL 8.58 60.16
Value of intermittent generation:
the 30% wind penetration case
• The total cost for the residual load is higher the value of wind is lower.
• We define the value factor (or utility factor) as the value of a fluctuating technology relative to that of a flat band.
• Value factor depends on technology, penetration level and country.
A wind providing fluctuating power (at 30% penetration level)
Result
• Non-parallel shift on the load curve.
• Significant changes in the composition of the generating mix (proportionally more peak-and medium-load capacity).
• The wind production replaces base-load technology on more than one-to-one basis.
Total cost Specific cost
[Bil. USD] [USD/MWh]
Original load curve 37.18 78.20
Residual curve 27.32 81.96